If you’ve got the winter doldrums and are anxious for an explosion of green, just wait until you see what’s coming to the area around the Maine Mall this spring.

The Long Creek Watershed Management District has announced a $850,000 landscaping project for Maine Mall Road and Gorham Road, which will include planting ginkgo and upright hornbeam trees in the median of Gorham Road, between Western Avenue and the Hannaford supermarket.

The idea is to shade the roadway in a particularly sensitive area of the Long Creek Watershed, in an area where 62 percent of the land is covered by impervious surfaces, including streets, buildings and parking lots.

According to Tamara Lee Pinard, a stormwater program manager at the Cumberland County Soil and Water Conservation District, who serves as executive director of the Long Creek group, an impervious cover of just 8 percent is enough to impact water quality. Because of heavy urban development, Long Creek does not meet minimum state or federal water-quality standards. That has landed it on the list of 31 “urban-impaired streams” in Maine, which have limited ability to support life.

By planting trees and roadside shrubs, and installing water filtering systems, Long Creek directors hope to remove pollutants and cool the temperature of stormwater that otherwise simmers on the asphalt before running into the watershed, which covers 2,240 acres and 127 properties in four municipalities, from Blanchette Brook tributary in the Col. Westbrook Industrial Park, along the 10 miles of Long Creek past the Maine Mall and out to the Fore River.

Cooling the runoff, and thus the stream itself, is a key component of restoring the health of Long Creek, says Pinard, who notes, “It’s all about the bugs.”

Advertisement

Still, there are realities to work past, not the least of which is overhead power lines.

“While I had dreams of majestic elms, Gorham Road is not exactly a tree’s dream,” said Pinard. “It’s a hostile environment.”

Even so, as developed as the Maine Mall area has become through the years, there are, even within the urban setting, pockets of opportunity.

“On Gorham Road, at the traffic light before WEX, there’s a gigantic median there. There’s a lot of traffic there, making it a hot spot. The potential for treatment there is excellent,” said South Portland Mayor Jerry Jalbert, who also is vice president of the Long Creek Watershed Management District board of directors.

“Even that little section of median, that’s important,” said Pinard. “If we can get even just these little benefits, that can help.”

But there’s also a psychological benefit, says Pinard. Along Maine Mall Road, Darling Avenue and Gorham Road, Long Creek directors initially wanted to narrow the road, in order to accommodate a new tree-lined median strip. That idea was rejected by the city, based on a 2011 Sebago Technics traffic study that showed average daily traffic of 16,000 vehicles on that stretch of road, which peaks at roughly 1,800 vehicles during the Friday noon hour.

Advertisement

The fear was that a reduction of lanes would create a choke point on what is considered to be an evacuation route. On top of that, property owners along the road, although they pay into Long Creek management, were not too terribly keen on losing the extra lanes gained in the last widening in 2009.

With that in mind, much of the work on the Maine Mall Road will be on the roadside, but that can help, too, says Pinard.

“In a lot of ways, this is a matter of changing people’s mindset that an area that has as much commercial activity as this can be an area that has trees,” she said. “We’re really trying to get people more accepting of the idea that it doesn’t have to be all asphalt.”

“We’re trying to have an area that’s developed, and can be redeveloped, but we’re trying to mimic Mother Nature as much as possible,” said Jalbert. “We’re actually trying to do better than Mother Nature in all these designs we put together.”

Also, in a separate project for 2015, which recently went out to bid for design and engineering, the Long Creek group will, among other things, look to install “hybrid bio-retention cells” along 66 acres of drainage area around the mall, of which 60 acres are impervious.

“These cells are essentially huge holes in the ground with some filtering media that has a circuitous route in which it sends the water, to give it as much time as possible to reduce the temperature, and to reduce the metals and the nutrients that we are concerned about for Long Creek,” said Pinard.

Advertisement

Meanwhile, Maine Mall manager Craig Gorris says he is working with Pinard to create an analysis of how much can be gained from planting islands of trees in the mall parking lot.

“That would be a significant investment for Long Creek, so it’s a question of whether the water temperatures would significantly reduce enough to justify that work,” he said.

However, General Growth Properties, which owns the 120-acre complex – apart from buildings owned by Macy’s and Sears – is not depending solely on the Long Creek group to transform its site. It has recently gone to bid, he said, to hire a landscape architect to create a five-year master plan for remaking the mall.

“Next year would be the first phase of that,” said Gorris. “Whether that includes additional trees, or shrubs, we don’t know yet. But that’s something we are going to do that will probably run several hundred thousand dollars in improvements.”

When the management district was formed two years ago, landowners of an acre or more of impervious surface were given a choice for how to meet Maine Department of Environmental Protection standards created to restore the stream to its former health. They could obtain individual permitting or join the district under a general permit, at a cost of $3,000 per acre, for 10 years.

“We operate on a cash basis because it was really important to the landowner that we not be taking out loans,” said Pinard. “This is a real public-private partnership. We want to do what’s best for the stream but we also want to do what’s best for the property owners in the district.”

According to Pinard, only one property owner, who controls four of the 127 district parcels, is not in compliance. Of the rest, one, the MTA Administrative Building, already has met state standards, while three (UPS, the Wyndham Hotel and Capital Automotive) have pressed on with individual permits already in progress when the Long Creek Management District was launched. The remaining 119 parcels fall under district auspices, said Pinard.

The total assessment to those property owners this year is $1.5 million, a figure that remains flat for the 2015 budget, with 63 percent of the fees paid by property owners funneled directly into construction projects. Another 21 percent goes into maintenance, 9 percent into water monitoring and 6 percent into administration.

With the planned construction work, the management district will run a $1.07 million deficit on $2.58 million in work for the next fiscal year, which starts July 1. However, that shortfall is covered by cash reserves, which totaled $1.42 million at the end of the 2013 fiscal year. The district is expected to stay in the black until 2019, the final year of the decade-long management plan, when it is projected to finish with an $11,623 debt.