BRIAN LEVITT, Bath’s wastewater treatment plant chief operator, explains on Wednesday how upgrades at the plant would make it more energy efficient and environmentally friendly. Bath is hoping to secure millions of dollars in loan and grant money from the USDA to fund the upgrades.
BRIAN LEVITT, Bath’s wastewater treatment plant chief operator, explains on Wednesday how upgrades at the plant would make it more energy efficient and environmentally friendly. Bath is hoping to secure millions of dollars in loan and grant money from the USDA to fund the upgrades.
BATH

The city of Bath is hoping to obtain $8.5 million in loan or grant money from the U.S. Department of Agriculture’s Rural Development sector to complete an upgrade of the city’s wastewater system.

THE WASTEWATER treatment plant in Bath, as seen on Wednesday, may be receiving upgrades this year if the city can secure $8.5 million in loan and grant money from the USDA. The matter will be discussed during Bath’s upcoming city council meeting on April 5.
THE WASTEWATER treatment plant in Bath, as seen on Wednesday, may be receiving upgrades this year if the city can secure $8.5 million in loan and grant money from the USDA. The matter will be discussed during Bath’s upcoming city council meeting on April 5.
A wastewater bond was approved by voters in November 2015, and since then the city has been exploring a number of options to make the upgrade happen.

“We are currently completing the necessary documentation to borrow the money,” said Bath Finance Director Juli Millet. “There is a chance that a portion of the loan total will come as a grant, but that is still unknown.”

USDA Rural Development requires a public hearing to inform the community of the request for funds. Millet said that hearing will take place during the city council meeting scheduled for April 5 at 6 p.m. at city hall.

Advertisement

The 2015 bond approved expenditures at the wastewater treatment plant on Town Landing Road — the most pressing being upgrades in dewatering equipment, aeration and structural work — with an estimated cost of $5.2 million. The bond also approved combined sewer overflow abatement improvements and upgrades throughout the city, with an estimated cost of $3.3 million.

Treatment plant chief operator Brian Levitt said that the plant’s dewatering equipment — which helps separate sludge from wastewater

— is “outdated technology.”

“We want to get rid of our belt presses and put in screw presses,” said Levitt. “Lewiston, Biddeford and a lot of the bigger cities have gone that way already, and so has Brunswick.”

Levitt said that the plant’s biosolids output — material that can be recycled after processing — now sits at around 20 percent. The new equipment would raise that number to as high as 35 percent.

“It would be better for the environment, a much more efficient option with less waste,” said Levitt.

Advertisement

Levitt said the sewer overflow abatement plan would help separate storm water from the sewer, which “is in everyone’s best interest.”

“Whenever it rains our sewers get inundated,” said Levitt.

The last major upgrade of Bath’s wastewater system occurred in 1997, and Levitt said that although city crews have done an admirable job up-keeping the system, it’s not energy efficient.

“We are barely holding it together,” Levitt said. “We desperately need this upgrade.”