4 min read

BATH

After working for about five years to find a way to tackle needed repairs on High Street, the roughly three-mile rehabilitation project was scheduled to begin earlier this week, stretching until November.

Crews won’t start with road milling and paving yet, however. For the first couple weeks they will do all of the underground work including sewer line repairs and raising manholes to allow for paving.

Ian Messier, an engineer with contractor Harry C. Crooker and Sons, told members of the public who attended a meeting last Thursday that workers will start in front of Hyde School where most of the drainage issues are. The rehabilitation project will move north to south.

Peter Owen, the city’s director of public works, said initially when the city began engineering for the High Street repair work, it was looking at a price tag of just under $2 million. Bath voters last fall approved a $2.5 million construction bond which the city didn’t want to spend all on one street project, so Owen said it began looking for a more economical project. The road was divided into six segments with different treatments planned based on specific road conditions. It will cost approximately $1.2 million.

Advertisement

Stretching from the Leeman Highway (Route 1) bridge to the West Bath town line, the three-mile section of High Street, which is Route 209, will be rehabilitated. One section, from Bumpy Hill Road to Winnegance, is in good shape and will receive only crack sealing to keep the water out, said engineer Jan Wiegman of Wright Pierce, who designed the rehabilitation.

From the Winnegance to the West Bath town line, reclamation and cement stabilization is planned. Wiegman said a large tiller will till up this section of road, pulverize pavement and mix it with some of the top surface gravel and then pack it down. As part of that compaction, he said cement will be mixed with the reclaimed material and water injected, creating a stiff base surface that will be covered with a base pavement. Next year at some point the road will receive a top layer of chipseal — asphalt with stones on top, which helps keep water out.

Messier said High Street will not be closed during construction, but will be reduced to a single lane. It will be narrow but there will be flaggers and it can be done, he said. Work may combine sections of road and will be very weather dependent.

The base pavement between the Winnegance and West Bath town line could be pushed back to the spring, Messier said. In that case Owen said the base would provide a regular riding surface. The contract requires the work be completed this year so the base pavement will only be put off until spring if weather dictates it is the best decision Owen said.

There were few questions from members of the public who attended the meeting, and who clapped at its conclusion.

“We’re thrilled,” said one woman, who thanked Owen for his part in obtaining a $500,000 grant from the Maine Department of Transportation to help fund the project.

Advertisement

“It’s going to get worse before it gets better,” said Owen. The road will be dug up before paving can take place and as vehicles drive over it, the road will then get bumpier.

“It’s going to be difficult for a while but we’ll get through,” Owen said, adding when the road paving is all done, the concern will then be speed.

dmoore@timesrecord.com

PROJECT TIMELINE

BATH — The city website dedicated to the High Street rehabilitation project (www.cityofbath.com/highstreet/) lists the project overview and timeline as follows:

Preliminary work: Before any work begins the city will replace existing culverts, install underdrains, repair damaged sewer lines and adjust manholes

Advertisement

Segment 1: Starts at the High Street bridge and extends approximately to the upper entrance of Hyde School. Treatment consists of resetting the curb along the west side of High street, milling the edges of the road and then resurfacing those edges and the entire road width. Work had been scheduled to begin in this segment earlier this week.

Segment 2 and 3: Begins approximately at the Hyde School upper entrance and extends roughly to the intersection of Marshall Street. Treatment includes milling of the entire road surface followed by pavement shim to reconstruct the crown of the road followed by a surface layer of pavement. Work is scheduled to begin in these segments Monday, Aug. 11.

Segment 4: Begins approximately at the intersection of Marshall Street and extends roughly to Bumpy Hill Road. This treatment includes a shim coat and full width overlay. Work is scheduled to begin in this segment Sept. 1.

Segment 5: From Bumpy Hill Road to Winnegance will receive crack sealing and no new pavement. Work is scheduled to begin in this segment Oct. 2.

Segment 6: From Winnegance to the West Bath town line. Full-width reclamation with cement stabilization is planned for this section of road, which then involves resurfacing with base and surface course pavement. Work is scheduled to begin in this segment Oct. 9.

Work schedules are conditional upon weather.