BRUNSWICK

Subcontractors at Brunswick Landing are busy cleaning up the residual effects of more than 60 years of gunnery practice at the former naval air station.

The $500,000 environmental remediation effort is required before the U.S. Navy can transfer the land to Midcoast Regional Redevelopment Authority for continued repurposing into a commerce and industrial park. Several military and civilian agencies surveyed the former base to determine which areas were most severely affected by decades of military use.

It is a two-phase project.

The initial phase is soil removal and treatment, which is scheduled to be finished in December.

Advertisement

The second phase begins in spring 2014, when native seedlings and other species will be planted that, in time, will grow the previouslycontaminated zones into as something that closely resembles their original, natural state, said Paul Burgio, the Base Realignment and Closure coordinator for the former Brunswick Naval Air Station.

Burgio is the “go-to guy” with regard to ensuring the former military installation is not an ecological disaster when ownership of the terra firma once again is held by the town.

The Navy estimated 1,500 tons of soil has to be removed and hauled to the state-owned Juniper Ridge Landfill in Old Town, a landfill about 15 miles northeast of Bangor that specializes in demolition and hazardous waste material disposal and incineration. It is operated by New England Waste Services of Maine LLC, a subsidiary of Casella Waste Systems.

Burgio didn’t have an estimate of how much soil already has been hauled to Old Town.

Other areas will be treated for soil quality, as well. But the primary treatment site is a 78-acre open field originally called the Brunswick Skeet Range. The Navy rebranded it the Orion Street Skeet Range, or OSSR.

Contractors managing the cleanup are USA Environmental of Oldsmar, Fla., and Parson’s Government Services in Boston. Turnerbased K&K Excavation, a subcontractor to USA Environmental, is working the removal, disposal, and site restoration, Burgio said.

Advertisement

One location, along Neptune Drive between the Orion’s Landing housing development and the quarters dedicated to the Construction Battalion “SeaBees,” already has been scraped of six inches of topsoil, selectively timbered and draped with a biodegradeable fabric to prevent erosion and runoff into nearby Beaver Pond.

Excavation at another zone, adjacent to the former commanders’ quarters on Captain’s Way, began in late October; that project is scheduled to be completed within a few weeks.