BRUNSWICK

School board members have approved more than $18,000 in renovation work beneath the stage at Brunswick High School to meet current fire codes.

The space, known as “the cave,” has been used to store props and set dressings, and for changing rooms during productions. But it’s been out of compliance for several years, according to district facilities and security manager Paul Caron, and the Brunswick Fire Department has run out of patience.

A plan to bring “the cave” into compliance has to be approved by the end of the fiscal year — which is Sunday — or the theater space effectively becomes off limits and unusable once school resumes in September.

Caron presented a plan to board members during their meeting Wednesday. He said adding partitions and sprinklers and other flame-containment requirements will cut the already limited storage space in half.

Advertisement

Board members have considered using off-site storage, portable on-site containers and even construction of a separate garage or shed that could be used to store athletic and other equipment, in addition to the drama department’s gear. But building a separate structure to meet the town’s codes and high school appearance standards could cost $78,000.

Hebert Construction of Lewiston submitted the low bid of $18,848. To pay for the project, $7,200 from theater rentals revenue and $11,600 would come from unspent funds in the energy account. The unspent funds are the result of districtwide savings due to electrical lighting and systems upgrades.

The board voted 5-1, with Janet Connors in opposition, to renovate “the cave” and delay a storage decision until more research can be done.