BRUNSWICK
Initial plans for a 17-lot housing subdivision at the end of Boody Street have been scaled back due to construction costs. The proposed Chamberlain Woods subdivision has been reduced to 10 lots on about 7.5 acres. Concerns about flooding at neighboring homes, however, remain.
On Tuesday, the Brunswick Planning Board approved a sketch plan review.
“The applicant received some estimates for road construction costs that were considerably higher than they were expecting,” said Town Planner Jeremy Doxsee.
One lot is already subdivided into two lots, one of which has a house on the corner of Belmont Street, leaving eight lots to be developed in total.
The planning board is limited in the actions it can take in the approval of a sketch plan review, in which the board only ensures that the applicant meets basic dimensional requirements of the zoning ordinance.
Town staff had determined that the applicant met those requirements, according to Planning Board Chairman Charlie Frizzle.
The applicant will take feedback from the board and incorporate it into their final plan.
The board had previously approved the applicant’s sketch plan for a 17-lot subdivision in October 2014. Neighbors at that time raised concerns about flooding.
“I like this a lot better than anything else that’s come up,” said Boody Street resident Colleen Congdon on Tuesday, referring to the new sketch plan. “I also like that it fits the neighborhood.”
However, Congdon had a number of other concerns, including snow removal and parking for Crimmins Field.
She also noted that a number of houses in the neighborhood have catch basins as a result of storm water issues in the area.
“We have some serious standing water and flooding issues, typically in the spring time,” said John Portela of Columbia Avenue on Tuesday. “Last year, we had a major water event in the middle of the summer … where our yard was completely flooded. We had over $ 6,000 worth of damage to my property.”
The problems have not gone away, despite drainage improvements that came with the construction of Crimmins Field, said Portela.
“I think the problem is, when you start digging down, you’re pushing up and out the water table,” said Portela. “That water is being displaced somewhere. When you’re putting in foundations, you’re creating pressure against that water table. My concern is that water is going somewhere, and it’s going into the rest of the neighborhood, and there doesn’t seem to be any plan to mitigate that movement of water.”
Curtis Neufeld of the firm Sitelines, representing Coastal Building and Investments, acknowledged “ there is a high ground water table in that neighborhood.”
“It’s a larger issue than a foundation would impact,” Neufeld said, adding that new homes will not have an adverse impact on surrounding, existing houses.
The subdivision will be serviced by town water and sewer and accessed by a private road, which is expected to become a public street.
An existing walkway that leads to nearby Crimmins Field will remain intact. Four acres of land on the site will not be developed.
The proposal will go to an independent firm, Sebago Technics, for review before coming back to the planning board.
jswinconeck@timesrecord.com
Comments are not available on this story. Read more about why we allow commenting on some stories and not on others.
We believe it's important to offer commenting on certain stories as a benefit to our readers. At its best, our comments sections can be a productive platform for readers to engage with our journalism, offer thoughts on coverage and issues, and drive conversation in a respectful, solutions-based way. It's a form of open discourse that can be useful to our community, public officials, journalists and others.
We do not enable comments on everything — exceptions include most crime stories, and coverage involving personal tragedy or sensitive issues that invite personal attacks instead of thoughtful discussion.
You can read more here about our commenting policy and terms of use. More information is also found on our FAQs.
Show less