A Regional School Unit 5 committee has proposed two less expensive options than the $16.9 million high school renovation plan defeated by voters in June — based on the results of a telephone survey.

The RSU 5 Board of Directors is likely to vote on a new package Sept. 25, in order to get a new bond referendum on the Nov. 5 ballot.

The Freeport High School Renovation Project study, conducted by Triton Polling & Research, became available to RSU 5 on Aug. 12.

A total of 445 RSU 5 residents — 71.6 percent from Freeport, 18.6 percent from Durham and 9.7 percent from Pownal — were polled.

Advertisement

To no one’s surprise, respondents identified cost as the major factor in voting against the June bond proposal. Freeport was the only town voting for the package.

The study found that some voters believe academic and athletic facility improvements should be separated, and still others want to scale back athletic improvements.

The result: The Renovation Advisory Committee has proposed a base project costing $14.6 million and a floating a bond to buy upgrades includ- ing a new track and synthetic turf at a cost of $1.7 million.

The base project would leave the school library in its current condition and move art — as well as science, technology, engineering and math programs — to the existing cafeteria.

Committee members Katherine Breer and John Simoneau read the committee’s findings to the board at Wednesday’s meeting at Freeport High School.

Simoneau told the board that the committee rejected several other cost reductions.

Advertisement

For one thing, the committee found, the need for renovations to the 1961 portion of the building is “undeniable and cannot be reduced.” There are safety concerns and a lack of Americans With Disabilities Act (ADA) compliance in portions of the facility.

Board Chairman Nelson Larkins of Freeport said a vote on the new bond article should take place at the Sept. 25 meeting.

Superintendent Shannon Welsh concurred. “It’s basically the last possible vote to get the warrant out in time,” Welsh said.

A total of 72.6 percent of respondents were between 41 and 70 years old — and 58 percent did not have children or grandchildren in the school system.

Six out of 10 indicated they might support the project if the overall cost were reduced.

Simoneau said later that the committee ruled out a turf field as part of the basic option.

Advertisement

Peter Murray of Freeport, however, vouched for the need of a turf field. “You get two and one-half times the playable field hours on turf,” Murray said. “Grass gets tired. That’s really important to mention. We’re field-poor right now.”

Instead, the committee favors repairs to the main athletic field. Two-thirds of the field hockey surface would receive drainage repairs and new grass.

The committee acknowledged that the fields would continue to see heavy use, and a “significant increase” in maintenance costs could ensue.

Scheduling of some game or practices at Freeport’s Hunter Road fields, or bussing athletes to Durham Community School might be necessary. Track atheltes would continue to be bussed to Bowdoin College for practice.

Also, the committee found, upgrades to the Pownal Road fields, owned by Freeport, might be necessary, and the costs borne by RSU 5.