2 min read

Adam Martin, plant manager at Harvey Performance Company’s Helical Solutions plant in Gorham, speaks at the town’s Planning Board meeting Monday. At right is project engineer Shawn Frank.  

GORHAM — The Town Planning Board Monday for the first time heard details about Harvey Performance Company’s expansion plans for a proposed plant at the former race track on Narragansett Street.

The Massachusetts-based firm is seeking permission to build a large plant in two phases on a 13-acre portion of the vacant horse racing track now owned by Shawn Moody’s company. Construction could begin in late spring or early summer.

The company manufactures high-performance machine tools. In presenting its plans at the pre-application discussion Monday, Vice President of Operations Steve Vatcher said Harvey has outgrown its current plant, Helical Solutions, in the Gorham Industrial Park.

“We’re growing and growing rapidly,” Vatcher said.

Advertisement

Vatcher is hoping for a construction start by summer. No material has been submitted yet to the Planning Department for review, but project engineer Shawn Frank of Sebago Technics said he will have a site plan ready for the Planning Department in a few weeks.

 “These folks are out of room,” Frank said.

Plans call for a project to be built in two phases.

Phase 1 is a 76,887-square foot, single-story building 22 feet high and with 172 parking spaces. A second phase calls for a 30,000-square-foot addition with parking for 115 more vehicles.

Planning Board member Michael Richman pointed out design standards for the project as specified in the Narragansett Development District. Requirements include building materials to be used and roof design.

Access to the plant will be a 1,300-foot road from Narragansett Street. Town Planner Tom Poirier said the access road would be built to industrial standards. Typical truck traffic to the site would be UPS and FedEx vehicles.

Advertisement

Narragansett Street is served by public water and sewer.

Helical now employs 80 workers and plans to add workers annually. Vatcher described the employees as highly skilled. Helical will vacate its current site and move to the new plant, Frank said.

Adam Martin, Helical plant manager, said it operates around the clock and has a weekend shift.

Planning Board Chairman Edward Zelmanow, noting people live across the street from the proposed project, said he and the Planning Board might want to visit the present plant to hear what operations sounds like.

No one from the public spoke at the meeting.

Robert Lowell can be reached at 780-9089 or email rlowell@keepmecurrent.com.

Adam Martin, plant manager at Harvey Performance Company’s Helical Solutions plant in Gorham, speaks at the town’s Planning Board meeting Monday. At right is project engineer Shawn Frank.

Comments are no longer available on this story