2 min read

BIDDEFORD — Biddeford, like a number of communities in Maine and across the country, is required to separate its sewage and storm water to reduce pollution in its rivers and watersheds.

For years, Biddeford has been replaced its old sewer system that carried stormwater and sewage in a single pipe with a two-pipe system, one pipe carries wastewater and another carries stormwater to reduce combined sewer overflow, or CSO, which can occur during major storms. During such weather events, pipes that carry both sewage and storm water together can overflow and untreated wastewater may contaminate the Saco River, Thatcher Brook and other local water bodies.

The latest corrective project will take place on Graham Street from Hannaford supermarket to Mason Street.

At $972,278, Dearborn Brothers Construction, Inc. of Buxton, was the low bidder for the project of the four firms that expressed interest in it, but one of only two that made a bid. City Council approved giving Dearborn the job on April 3.

City Engineer Tom Milligan said Dearborn has conducted similar projects for the city in the past and is currently working on the sewer lines on Hills Beach Road.

Advertisement

“They’re a pretty reputable firm,” he said, adding “they’ve done great work for us” in the past.

Milligan said he expects the approximately 1,000-foot project to begin sometime this spring and be completed by mid-summer. However, he said, the exact timeline has yet to be nailed down. A traffic flow plan must also be created, he said, and will be reviewed by the Police Department and City Council. Milligan said he believes creating detours around the project should be fairly easy.

The project is being funded by one of two bonds residents have voted for in the last 10 years, one for $4.9 million in November 2008, and another for $3.925 million in November 2015.

Since the early 1990s, the city has been working to correct its CSO problem, after an Administrative Order by the U.S. Environmental Protection Agency and a Consent Agreement by the Maine Department of Environmental Protection were filed against Biddeford. With the passage of the bonds, the city has been making steady progress.

About 85 percent of the pipework has been completed, Milligan said.

However, he said, more options need to be put in place “to reduce additional inflow and infiltration” such as pollution coming from roof drains.

Advertisement

“We’re getting close to the end of what we can take out by getting the catch basins out of the combined sewer,” Milligan said.

— Associate Editor Dina Mendros can be contacted at 282-1535, ext. 324, or dmendros@journaltribune.com.


Comments are not available on this story. Read more about why we allow commenting on some stories and not on others.