Increasing parking in the area through the creation of a parking garage has been viewed as one solution. The city of Biddeford and the engineering firm Desman Associates have selected three potential sites as the location of a proposed parking structure that would contain over 400 spaces, these include: the Washington and Federal streets lot, the site of the former Maine Energy Recovery Company and Pepperell Plaza. The first two are city-owned sites, the third is privately owned.
Based on a number of factors like efficiency, cost, expansion capability, costs of operation and maintenance, user convenience, and potential for mixed use, the former Maine Energy site received the highest rating, with the Washington, Federal streets site receiving the lowest rating.
The structure would be constructed with precast concrete, which John Whipple with Desmond Associates described as “very durable.” He said the firm would design the building to “fit into the city in a likable presence.”
Some of the problems with the Washington, Federal street site is that it would require building a seven-story structure to achieve the more than 400 spaces the city wishes a parking structure to contain. Not only does that not fit in with the area, where buildings are generally one to three stories, costs increase for higher level structures.
The Pepperell Plaza is a privately-owned site, which has a number of geotechnically issues, such as canal tunnels, that could be costly to deal with.
The former Maine Energy location would have an efficient layout, would be easy to expand and could include retail or other mixed use spaces in or near the structure.
Cost estimates for the Federal, Washington streets site range from $13 to $12. 4 million, for the former Maine Energy site, $11.6 to $12 million, and $11 to $11.6 million for Pepperell Plaza.
City Manager James Bennett said the cost would not be born by taxpayers, but would instead be paid for by a revenue bond — which does not require a ballot referendum question — as well as funds from the Tax Increment District fund, which is paid for through fees on new valuation.
“Bond debt does not go on the mil rate,” Mayor Alan Casavant said.
The council will likely hold a workshop in January to talk about whether they want to go ahead with constructing a parking structure, and if so which of the three sites they favor. Bennette said he thought the Federal, Washington site was the least desirable.
If the council greenlights the project, it would take about two years to complete.
Because of the timeline for completion, Councilor Mark Lessard said “If there is interested in doing this and interest in gaining economic development” the council should make a decision as soon as possible.
— Associate Editor Dina Mendros can be contacted at 282-1535, ext. 324, or dmendros@journaltribune.com.
Comments are not available on this story. Read more about why we allow commenting on some stories and not on others.
We believe it's important to offer commenting on certain stories as a benefit to our readers. At its best, our comments sections can be a productive platform for readers to engage with our journalism, offer thoughts on coverage and issues, and drive conversation in a respectful, solutions-based way. It's a form of open discourse that can be useful to our community, public officials, journalists and others.
We do not enable comments on everything — exceptions include most crime stories, and coverage involving personal tragedy or sensitive issues that invite personal attacks instead of thoughtful discussion.
You can read more here about our commenting policy and terms of use. More information is also found on our FAQs.
Show less