A map details the area of work for a planned drainage improvement project on Mile Stretch Road to be completed this spring. SUBMITTED GRAPHIC/Courtesy of City of Biddeford
A map details the area of work for a planned drainage improvement project on Mile Stretch Road to be completed this spring. SUBMITTED GRAPHIC/Courtesy of City of Biddeford
BIDDEFORD — The Biddeford City Council granted authorization of a nearly $630,000 contract to improve drainage along Mile Stretch Road on Tuesday evening.

The council voted unanimously to sign a unit cost contract with Pratt and Sons, Inc. of Mechanic Falls for the construction of the Mile Stretch Road Drainage Improvement Project in the amount of $629,803.

Funding for the work comes in part from a Maine Department of Transportation Municipal Partnership Initiative, or MPI, grant. In addition, a required city match will come from a 2009 Road Improvement Bond passed by voters.

A portion of Mile Stretch Road in Biddeford is pictured Wednesday, with water left undrained on the side of the road. The Biddeford City Council approved authorization of a nearly $630,000 contract to improve drainage along the road on Tuesday. ALAN BENNETT/Journal Tribune
A portion of Mile Stretch Road in Biddeford is pictured Wednesday, with water left undrained on the side of the road. The Biddeford City Council approved authorization of a nearly $630,000 contract to improve drainage along the road on Tuesday. ALAN BENNETT/Journal Tribune
City Engineer Tom Milligan said in a March 28 memo that six construction firms requested plans and specifications for the work, while only two — including Pratt and Sons, Inc. — submitted bids for the project. Gorham-based Gorham Sand and Gravel submitted a bid of $818,024.45.

Plans have been in the works for nearly two years to perform drainage improvements on Mile Stretch Road from Bridge Road to Lester B. Orcutt Boulevard.

Advertisement

Milligan said Wednesday that the road’s level grade contributes to improper drainage of water runoff in the area, which closely borders the waters of Biddeford Pool.

“That lower section of the road from Bridge Road that goes into the (Biddeford) Pool beach area is pretty flat and there’s no real elevation difference, so we’re putting in some drainage pipes to drain some of that water,” Milligan said.

Following the installation of drainage pipes, Milligan said, construction crews will work on repaving the nearly 6,000-foot-long roadway, which is one of the only access points to the Pool.

Milligan said survey work on the area was completed in the past year, and design of the project was completed within the last six months. The city has also held meetings with the neighborhood group Biddeford Pool Improvement Association to get input on local drainage issues.

Milligan said the project is on “fast track” to be completed this spring, by Memorial Day, in hopes of beating the rush of summer residents who will soon flock to the scenic coastal area.

Until then, he said, traffic will likely be reduced to one lane at a time while construction crews work to install piping and later pave the roadway.

Advertisement

“The contractor needs to submit a traffic management plan, but I would suspect they’ll be alternating one-way traffic. … There’ll probably be some delays and that’s why we’re doing it this time of year, just to beat the summer folks,” he said.

“It’s a pretty aggressive (construction) schedule,” he added. “If we can get all the drainage work done by (Memorial Day), we’re in good shape. The cards all have to fall in the right place.”

— Staff Writer Alan Bennett can be contacted at 282-1535, ext. 329 or abennett@journaltribune.com.