BIDDEFORD — MaineDOT representatives spoke at a public meeting at City Hall earlier this month to detail two state-orchestrated paving projects that will be occurring on Main Street in the near future.
DOT Project manager Robert Betz explained that the projects are pegged to start in the fall of this year, with the “bulk of the work” extending through the end of 2016.
The first is a simple “mill and fill” project on Main Street, from Alfred Street to Elm Street, said Betz. “It’s strictly a paving project,” he said. “It should be a pretty short duration kind of job.”
The $185,000 project will only take about a month to complete, he said, and the city will cover 10 percent of its cost, while the state will cover another 10 percent, and the federal government will pay the remaining 80 percent.
Betz said the second DOT project, however, which involves the area of Main Street from Elm Street to Railroad Avenue, will be more extensive.
“What we have here is a road that needed more than just a paving job,” he said. “The cross slope on the road is very steep. … A good indication of the issues that you can have there is if you park too close to the curb and you open your door, it drives right into the curb because the road is too steep.”
Betz said as of now the plan is to remove all of the existing pavement on that roadway, re-grade the gravel there and pave over everything. The road will also be narrowed to extend its curbline, he said.
“There are a few locations where, for instance, fire hydrants or telephone poles are actually in front of the curb and are in a position to get struck by cars,” said Betz.
This project is expected to cost $1.25 million, he said, and it will be funded in the same manner as the first ”“ with $1 million in federal funding and $250,000 in city and state funding. Betz said the DOT plans to hire a contractor by September and anticipates the project will be completed by December of next year.
At the meeting, Brian Sanderson, a DOT appraiser, explained how the project will affect property owners whose land abuts the construction zone.
“This project will only require temporary construction rights. … We’re asking permission to go onto your property for the duration of the construction, and when the construction’s over those temporary rights go away,” he said.
Sanderson said that by mid-April the affected property owners will be contacted by mail. Then an appraiser will inspect their properties, he said, and a negotiator will eventually determine how much compensation each one will get for the impacts to his or her property.
Biddeford Public Works Director Guy Casavant also spoke at the meeting to briefly detail three utility projects that will be taking place before the two from DOT. As soon as it’s warm enough, he said, there will be work to extend a gas line on Main Street, from Alfred Street to Elm Street. Casavant said a new water main will also be installed on Elm Street, from Main Street to South Street, and there will sewer work in the area, too.
In an email Tuesday, Jennie Franceschi, the city’s planning engineer, said it’s too early to assess how much the DOT projects will affect traffic flow on Main Street.
“The contractor will have to provide a traffic control plan, so until we have that we won’t know the proposed impacts,” she said, adding that once a traffic control plan is provided, it will be reviewed by city staff as well as Biddeford Police Chief Roger Beaupre.
— Staff Writer Angelo J. Verzoni can be contacted at 282-1535, ext. 329 or averzoni@journaltribune.com.
Comments are not available on this story. Read more about why we allow commenting on some stories and not on others.
We believe it's important to offer commenting on certain stories as a benefit to our readers. At its best, our comments sections can be a productive platform for readers to engage with our journalism, offer thoughts on coverage and issues, and drive conversation in a respectful, solutions-based way. It's a form of open discourse that can be useful to our community, public officials, journalists and others.
We do not enable comments on everything — exceptions include most crime stories, and coverage involving personal tragedy or sensitive issues that invite personal attacks instead of thoughtful discussion.
You can read more here about our commenting policy and terms of use. More information is also found on our FAQs.
Show less