ALFRED — Got road work? The Maine Department of Transportation Work Plan is out, and it looks like there will be new pavement and new bridges in some communities as well as engineering for future projects and more this year in central and western York County.
The Work Plan contains projects that are being funded this year and projects in various stages of planning for 2016 and 2017. DOT Commissioner David Bernhardt, in a memo included in the plan, said the 2016 and 2017 projects are subject to change, so for this story, we’ve mainly looked only at those set to take place this year.
In Biddeford, Planning Engineer Jennie Franceschi explained some of the projects slated for the city this year.
For those who commute into or out of Biddeford, there will be a paving project on Alfred Road (Route 111). Paving will be done about half a mile east and one mile west of Pomerleau Street. Franceschi said that project will be done at night, when there’s less vehicular traffic.
A replacement bridge over the Saco River on Pine Street may go to bid in the fall, she said, and rehabilitation of the Elm Street Bridge on Route 1 is actually for the underside of the structure.
Paving on portions of Adams and Jefferson streets is set for sometime this summer, while Main Street paving and construction plans will likely go to bid in August, and may get moved to the spring of 2016, she said.
In Biddeford, a public meeting on this year’s state road work plans is set for 7 p.m. on Feb. 12 in the City Council chambers. The meeting had been scheduled for earlier this week, but was postponed due to the snow storm.
“We’re very pleased with what we have received and what we’ll be receiving in the next few years,” Franceschi said, pointing to a planned future intersection reconfiguration at Main, Hill and Water streets and a Route 1 signal coordination that includes three signals in Biddeford and upwards of 10 in Saco; the traffic signals are set to be updated with new components among other improvements.
A similar signal reconfiguration project is in the planning stages in Sanford, said Public Works Director Matthew Hill. The project includes replacing a dozen signals and bringing intersections up to Americans with Disabilities Act standards, Hill said. While planning for that project is ongoing, the work itself has not been funded for this year.
Sanford has had a “flurry” of state road work, including a major paving project on Route 109 from Main Street north to the Shapleigh line over the past couple of years. So while the state’s Work Plan doesn’t include a lengthy list of Sanford projects this time around, there are a couple, including the purchase of equipment at Sanford Seacoast Regional Airport and preliminary engineering for a future highway construction project on Cottage Street (Route 202), just north of Lafayette Street and extending northerly towards the Southern Maine Health Care campus.
State Rep. Anne-Marie Mastraccio, a former city councilor, expressed her support for the Sanford plans.
“These projects have been in need of funding for quite some time now,” said Mastraccio, a member of the Labor, Commerce, Research and Economic Development Committee in the Maine Legislature. “It’s a relief to finally see them taken off the back-burner and set in motion.”
Sanford has partnered with the state on a number of prior projects, like work on Oak and Pleasant streets and Shaw’s Ridge Road, and would like to do so again, Hill indicated.
He noted Sanford has a couple of intersections that are a priority for attention, including the Route 4 and School Street intersection and the one at Cottage and River streets.
One project that will affect those commuting across Route 111 and those who use Hill Road in Arundel to enter Route 111 is the installation of a traffic signal at the intersection there. A long time in the planning, DOT has injected $746,000 into that project. The Work Plan itself indicates there’s no signal included, but project manager Ernest Martin said that is a typo.
A signal is indeed included in the project, he said Friday, along with a right-hand turn lane heading west on Route 111 for Hill Road commuters and a new culvert. Martin said the project will likely be advertised for bid at the end of March, with construction set to begin after July 15.
— Senior Staff Writer Tammy Wells can be contacted at 324-4444 (local call in Sanford) or 282-1535, ext. 327 or twells@journaltribune.com.
Comments are not available on this story. Read more about why we allow commenting on some stories and not on others.
We believe it's important to offer commenting on certain stories as a benefit to our readers. At its best, our comments sections can be a productive platform for readers to engage with our journalism, offer thoughts on coverage and issues, and drive conversation in a respectful, solutions-based way. It's a form of open discourse that can be useful to our community, public officials, journalists and others.
We do not enable comments on everything — exceptions include most crime stories, and coverage involving personal tragedy or sensitive issues that invite personal attacks instead of thoughtful discussion.
You can read more here about our commenting policy and terms of use. More information is also found on our FAQs.
Show less