NORTH WINDHAM – The first phase of improvements to Donnabeth Lippman Park in North Windham is becoming a reality after the Windham Town Council voted unanimously to award a $139,137 contract to Drew Corp. of Lovell.

Drew Corp. will design and build a new access road from Route 302 into the property and improve parking.

The 123-acre park surrounds Chaffin Pond on Route 302 and was formerly owned by the Portland Water District, which used the pond as a backup water supply. For many years, the public has had access to trails around the pond for hiking and snowshoeing. Fishing is also popular on the property, said Town Manager Tony Plante.

The town of Windham bought the property in May 2011 for $400,000 from the Portland Water District after receiving full reimbursement from Martin Lippman, a Standish resident and North Windham business owner whose wife, Donnabeth, has since passed away.

According to Plante, the council awarded the bid to the Drew Corp. for $126,487 for the work, with an authorization of an additional $12,650 for engineering and testing.

The initial park improvements, which are considered Phase I of a future overhaul of the property for recreational purposes, are being paid for with $50,000 from the town’s land and facilities capital improvements account and the remaining $89,137 from the parks and recreation’s budget surplus, Plante said.

Advertisement

In December of 2011, the town hired Portland design firm Mitchell & Associates to develop a park master plan that encompasses several concepts for the park, based on input from Windham residents and park users. Several meetings have since been held to solicit ideas and concepts for the park property, Plante said Tuesday.

As a result of the meetings, two conceptual plans for the park have been developed. The first concept, he said, includes recreational fields, trails and playgrounds. The other concept is less intensive and focuses solely on trails, with elevated boardwalks along the wet areas of the trails, picnic pavilions and a play area.

Dustin Roma, a civil engineer with Portland consulting firm Milone and MacBroom, presented the council with initial design plans for widening the access road and a future parking area at Tuesday’s meeting, explaining he’s received all the necessary permits from the Planning Board and the Maine Department of Environmental Protection and is arranging a site visit prior to construction.

“It’s narrow and too long,” Roma said of the dirt road leading into the park. “We want to widen it up so we can have vehicles pass one another,” which will eventually be made safer with yield signs, he said.

Councilors said they expect that the signage at the park’s entrance will recognize Martin Lippman’s donation to the town for the purchase of the property.

“It’s been an unofficial natural area for a long time, but it wasn’t until the town acquired the property from the water district that we really looked at how to develop it more actively as a multi-use park for the community, in a way that reflects the natural character of the property,” Plante said.

While initial engineering is complete, Plante said further engineering would be needed once the council decides exactly what it wants to erect for amenities, including possible recreational fields. According to Plante, the timeline could span several years.

“We may end up developing playing fields on land that is more well-suited to it,” Plante said. “But that’s part of the master plan as it sits right now. It will take a while. We will have to be patient and work at this diligently, but the council right now is committed to realizing the vision of a community park.”

Comments are no longer available on this story