WINDHAM – A preliminary design of the River Road reconstruction project, extending 6 miles from routes 202 to 302, will be unveiled at a public hearing Wednesday, May 30.

While the road was paved last year with a coating of asphalt, the real reconstruction project won’t start until fall 2013, and will entail smoothing out the dips, twists and turns, in addition to widening the travel lane and installing breakdown lanes.

With lots of questions swirling as to the redesign of the busy commuter road, Ernie Martin, project manager for the Maine Department of Transportation, will be on hand Wednesday to address concerns from the public.

“We’re there for comments. Are there drainage issues? Is there anything related to personal property that we need to be aware of? What are the utilities out there?” Martin said of Wednesday’s meeting. “Basically, what are your comments on River Road? What are you seeing out there? What do you like, what don’t you like? That’s what this meeting is about.”

For the most part, Martin isn’t expecting many new concerns to come to light. He has been working with a large group of Windham residents and town officials for more than a year. The state’s effort to work with locals long before a project gets under way – known as Context Sensitive Solutions – is a new concept for the department and is meant to identify problems early on.

“Through the Context Sensitive Solutions process, which entailed a large group of local people, we’ve hammered out a lot of the issues on Windham’s River Road already so we’ve had so much dialogue with folks from the town and we’ve had a lot of contact with people out there, and they’ve given us a pretty good idea of what’s out there,” Martin said.

Advertisement

At the public hearing, a linear map showing the preliminary design of the roadway will allow locals a chance to see details of the design. And while the roadway will not veer from its right of way, property frontage could be impacted, since the road will be widened, Martin said. Specific details of how roadway reconstruction will impact abutters – an issue that was raised by the public at the initial public hearing in 2010 – will be discussed at a planned public hearing in the fall, Martin said.

“We’re really not going to get too much into that right-of-way discussion at this meeting. We’re not there yet. So we’re going to come back later in the fall for a final public meeting and that’s where the right of way will be more talked about,” Martin said. “Obviously, our intent is to rebuild the road with as little property impact as possible. But there will be property owner impacts. We’re just not sure of the severity at this time.”

The public hearing also pertains only to the northern part of River Road, which has received $6 million in state funding. River Road’s lower half, from Route 202 to the Westbrook line, has not received reconstruction funding but is a candidate in the transportation department’s 2014-2015 biennial work plan, Martin said.

Travelers of the lower section have seen several surveying companies, including crews from AMEC, Gorrill Palmer and Sebago Technics, this month. Martin said he wants to have the lower half surveyed and “ready to go” should the Legislature grant funding.

“I’m having the crews out there surveying that piece south of Route 202 so once we’re done with this piece we can roll right over and get that other piece designed and ready for future construction funding when it becomes available,” Martin said.

Martin Shuer, a resident of the northern section of River Road and member of the Context Sensitive Solutions group, which at one point had about 25 members, is hoping the public turns out for Wednesday’s meeting.

Advertisement

“I would encourage members of the public to attend the public hearing on May 30 to hear MDOT present the design work they’ve done to date on the River Road project,” said Shuer. “[The hearing] will provide a good opportunity for members of the public to engage in a question-and-answer session with them about any comments and concerns they have about the project.”

Charlie Haddock, another member of the local group, also encourages locals to turn out Wednesday night to learn more about the project, which has been a long time in coming for Lakes Region commuters who use River Road to drive to work in Westbrook and Portland.

“The project is moving forward. It’s a little later than we had hoped, but it is moving forward,” Haddock said.

Surveyor Joel McPike of Amec Engineering, based in Portland, uses a GPS-assisted transit device (now called a total station) to determine road contours along River Road last week. McPike was working with Jim Jackson, seen across the roadway. (Staff photo by John Balentine)