Frustrated commuters will get some relief when the long-awaited Gorham Bypass opens seven months ahead of schedule for traffic on the evening commute of Friday, Dec. 5.

The $28.8 million bypass will divert commuter and truck traffic, including gasoline and oil tankers, from Gorham Village. The bypass links routes 114 (South Street), 202 (Narragansett Street) and 25 (Ossipee Trail).

The bypass is expected to relieve traffic congestion in Gorham, which has become infamous for long waits, particularly in the morning and evening as commuters travel to and from work. Many commuters have made their own bypasses by cutting through residential neighborhoods in Gorham.

“We’re going to have a party, a block party when the bypass opens,” said Sonja Frey, who lives on Solomon Drive and expects traffic to decrease in her neighborhood.

Mark Latti, a spokesman for the Maine Department of Transportation, said the bypass, which is opening earlier than expected, will become a part of Route 112.

Larry Kuusela, project supervisor for Shaw Brothers Construction Inc., of Gorham, which built the bypass, said Monday the completion date was June 13, 2009.

Advertisement

“We’re seven months ahead of schedule,” Kuusela said Monday as he drove a Shaw Brothers pickup truck along the 3.5-mile bypass. “It’s ready now.”

Kuusela, a Gorham native who studied engineering at the University of Maine at Orono, said the construction company worked 15-hour days on the bypass. “We worked dawn to dusk,” said Kuusela, who grew up in Little Falls and is well acquainted with Gorham’s traffic woes.

Latti said state and town officials will cut a ribbon at 1 p.m. Dec. 5 at the bypass’s roundabout intersection with South Street.

The bypass features three roundabouts, which are smaller than traffic rotaries, at three intersections of the bypass. Kuusela said roundabouts, which are popular in Europe, will help keep the traffic flowing better than red lights.

Plans and hopes for a bypass began decades ago in Gorham to relieve traffic congestion. Latti called it a “50-year wait.”

As many as 40,000 vehicles each day travel through the intersection where routes 114, 202 and 25 converge in Gorham Village.

Advertisement

Frey has lived in Gorham since 1985 and has seen a marked traffic increase on the street where she lives.

Gorham Town Councilor Burleigh Loveitt, who served on the study committee that paved the way for construction, said Monday the bypass follows a path similar to one designed 56 years ago by then Selectman Austin Alden.

“It’s the beginning of a solution to some of Gorham’s traffic problems,” Loveitt said.

Congress earmarked money for the bypass, a southerly route, but a northerly bypass leg around Gorham Village was not funded. Town Councilor Shonn Moulton, a village business owner, said the bypass is a big, first step but agreed with Loveitt that the town needs more.

“It’ll rejuvenate downtown,” said Moulton, an advocate for a more pedestrian friendly village.

Moulton hopes that someday the bypass be connected to the Maine Turnpike. Loveitt said Gorham needs either another new roadway or improved existing roads connecting South Gorham to South Portland.

Advertisement

Shaw Brothers Construction Inc. was awarded a $10.2 million contract to build the bypass and began work in August last year. The construction pricetag didn’t include three bridges, which were a separate contract.

Construction wasn’t problem free. A 1,200-foot stretch of the bypass caused a delay when ground shifted last year because of unstable sub soils.

Kuusela said the shift “blew up” Brandy Brook, which had to be relocated. “We worked 24 hours a day just pumping water for six weeks,” Kuusela said.

In building the bypass, the construction company blasted a “lot of ledge” and relocated 172,000 yards of material. Kussela said 225,000 yards of road fill and 100,000 yards of gravel were trucked in.

The bypass is all paved and striped as opening day nears. One driver sped illegally along the bypass Monday, although it is clearly marked closed. Kuusela said police patrol the bypass and a ticket for trespassing is $138.

As he drove along the bypass, Kuusela slowed and stopped for a large flock of turkeys crossing the two-lane bypass. He’s watched the turkeys grow from spring chicks to adult birds. He said the turkeys roost at night in trees along the new roadway.

Advertisement

The area has a significant wildlife population. “We’ve seen deer all over this place,” Kuusela said.

He said 125-foot bridges instead of culverts over Gully and Nute brooks were designed for wildlife crossings. Fences are being erected along the bypass. While welcoming the bypass, Frey worries that the deer will jump the fences.

Also to protect wildlife, weirs to allow fish passage were placed in pipes under Flaggy Meadow Road for Brandy Brook. A pool near the bypass was constructed to keep frogs and salamanders off the highway.

The construction equipment that built the highway is as modern as the bypass itself. Kuusela said the bypass was constructed with bulldozers and road graders equipped with global positioning systems and computer screens. He said models of the bypass were designed in company offices. Discs were then placed in computers on equipment for operators to read.

“It’s a new world,” Kuusela said.

After what one state official described as a “50-year wait,” the Gorham Bypass will open Dec. 5, seven months ahead of schedule.Larry Kuusela, project supervisor for Shaw Brothers Construction Inc., said the construction company worked 15-hour days on the bypass.