Construction could begin within a week on the long-delayed Wal-Mart Superstore at Scarborough Gallery.
Officials from Wal-Mart are scheduled for a meeting on Wednesday with the town code enforcement office to obtain a building permit. Construction of the 212,000-square-foot building has been held up for more than a year because of excessive moisture in the soil, caused by last year’s heavy rainfall and the presence of Presumpscot clay in the ground, a material that holds moisture.
A 138,000-square-foot Lowe’s store, whose construction was also delayed due to moisture, is finished, and the store is set to open on July 31.
The rest of Scarborough Gallery, a development located between I-295 and Spring Street, should start to fill up soon with smaller businesses, according to Code Enforcement Officer Carroll Shepard.
“Once Lowe’s or Wal-Mart opens, I expect the other restaurants to follow suit,” Shepard said.
Two chain restaurants already have been approved by the planning board. Red Robin, a bar and burger joint, has more than 350 stores around the country. The Scarborough location would be its second in Maine, with another in Augusta. The Texas Roadhouse chain has more than 260 locations, including one in Bangor. The restaurant specializes in steaks, ribs and southern foods, like country-fried chicken.
McDonald’s is also eying a spot, and is scheduled to first appear in front of the planning board on Monday. According to Town Planner Dan Bacon, the restaurant’s design is different from a typical McDonald’s. The building will be brick with awnings.
“It’s a different style,” said Bacon.
Harvey Rosenfeld, president of Scarborough Economic Development Corp., said he will be interested to see how the town’s design standards, that include peaked roofs and cupolas, will affect the look of the McDonald’s. According to Bacon, the current design of the McDonald’s is still a flat roof.
“My sense is there will be more work to be done,” Bacon said.
Ben Divine, a principal of KGI Properities, the developer of Scarborough Gallery, said there has been “real, good interest” from businesses who want to move in, though he declined to name them. The planning board has a site-review plan on its Monday agenda for an unnamed, 91,000-square-foot building in Scarborough Gallery.
“We’re excited,” Divine said. “It’s going well. We just want to get these buildings open.”
Before construction can begin, it has to be determined that the site is ready. About a year and half ago, soil was brought in to solidify the moist ground at the site in a process called “pre-loading.” During pre-loading, soils are brought in to create a mound of earth that replicates the weight of the building, said Town Manager Ron Owens. The soil then settles, compacting the ground underneath the building site by eliminating the moisture.
When soil is brought in to create a pad for construction of large buildings like a Wal-Mart Superstore, it’s not unusual for the soil to settle between 6 inches and a foot over the period of a year, according to Owens. However, the soil at Scarborough Gallery site sunk more than 3 feet in the past year and a half.
Bringing in soil to compensate for wet soil is not unusual, according to town officials. Other nearby projects, like the Christmas Tree Shop and the Marriott Hotel, have had to use the same process.
According to Town Engineer Jim Wendel, some professional engineers are saying the soil is still settling.
“There are a couple of opinions from opposite ends,” Wendel said.
Shepard said he received a letter from the developer’s engineer that said the site was ready to be built on, and until he gets another letter saying otherwise, he expected the building permit to be issued on Wednesday, after The Current deadline.
Divine said once the permit is issued, construction would begin within a week or so. Divine said he expects the Wal-Mart Superstore to open in the first quarter of 2008.