The state is about to decide if long-delayed improvements to Route 114 in Gorham will finally be getting underway.

The Maine Department of Transportation will announce Friday, July 14, whether it would award a contract for a project for major reconstruction of the portion of Route 114 known in Gorham as Fort Hill Road.

R.J. Grondin & Sons, a Gorham contractor, submitted the “apparent” low bid of $6.6 million for the project, according to Herb Thomson, the Maine Department of Transportation’s communications director. Thomson said the bid opening came on June 14 and the department had a 30-day period before deciding whether or not to award a contract.

Earlier this year, the state estimated the reconstruction of the highway would cost $4 million. Highway improvements would straighten some curves and improve visibility for motorists traveling on the busy stretch of road

Bob Hough, an assistant project manager with the Maine Department of Transportation, said in April that the project would be a “major reconstruction” of the Route 114 highway from the University of Southern Maine to the intersection with Route 35 in Sebago Lake Village.

The project has been on the drawing board for some time. The state once anticipated that construction might have gotten underway this spring. The highway is dotted with residential homes and a scattering of farms.

Advertisement

That part of Route 114 rolls over hills and through a bucolic countryside towards Sebago Lake. Fort Hill, the highest point, has a park, which affords a scenic view of the White Mountains to the west.

Gorham Town Manager David Cole said Friday that he expected the project to move forward. He said Central Maine Power has been setting new utility poles in connection with the project.

Cole believed the highway would remain open during the reconstruction although he expected some traffic delays. “I can’t imagine them closing the road,” Cole said.

The highway is a major arterial used by traffic hauling boats on trailers and other vacationers to and from Sebago Lake in the summer besides the daily year-round commuter traffic. Thomson said Tuesday that an average of between 4,000 to 5,000 cars a day use that part of the highway.

Mike Phinney, chairman of the Gorham Town Council, said a lot of motorists use Fort Hill Road as a bypass around the rush hour bottleneck in Gorham Village. “They’ll try their best to keep traffic moving,” Phinney said about the reconstruction.

Phinney, who is vice president of Phinney Lumber Company on Fort Hill Road, said reconstruction would reduce the amount of a curve in the highway in front of their business. He also said the now dangerous intersection of Fort Hill Road with North Street would be redesigned. Phinney said the intersection is the scene of a lot of accidents now.

He also expects delays for traffic at times during the project and said his company would likely have to look for alternative routes for its trucks. Phinney said reconstruction would create some temporary difficulty for the lumber company.

But Phinney looked forward to the results of the improvements along the highway. “It (the highway) will be nice when they get it done,” Phinney said.