3 min read

The Scarborough Town Council has determined the duties and membership of the School Building Committee that would oversee the construction of the upcoming school construction projects if necessary.

The committee will handle the construction portion of the project, including preparing bid documents, awarding contracts and hiring the clerk of the works.

Previously, the Scarborough Board of Education formed the building committee, which provided oversight of school building projects.

But following the controversy regarding the quality of construction at the high school, councilors agreed to utilize a state law that gives them the authority to form a construction committee to oversee the project.

The school district is considering building a new intermediate school and a major addition to the middle school that is estimated to cost around $50 million.

The School Board has formed two committees to develop plans and designs for these projects. Those groups will present the plans to the public for a referendum vote in November. If voters approve the project, then the council’s building committee would be formed.

Advertisement

The committee will be comprised of one member from both the Town Council and School Board, a faculty member from both the middle school and intermediate schools. It also will include one member from the school building committee, three residents, a commercial developer and a builder.

No one from the town or school administration is included on the committee, although there are plans for the school’s facilities manager and a member from the code enforcement department to act as liaisons.

Someone from the code enforcement department was originally listed to be on the committee, but was removed since some councilors thought there might have been a potential for a conflict of interest.

Library renovation question coming

Town Council Chairman Steve Ross and Councilor Jeffrey Messer said they would abide by voters’ wishes regarding an advisory referendum question on the June ballot about a $6.8 million renovation and addition at the library.

The advisory question is designed to gauge public opinion about the project. Normally the question would go to a referendum vote for a bond, but the library is eligible to receive a U.S. Department of Agriculture loan with a low interest rate to pay for the project. The town would make the annual payments for the library.

Advertisement

While the council does not necessarily have to follow the response to the referendum, Ross and Messer said they would do so.

Councilor Shawn Babine questioned if he could support the project given the cost and public response he has received since the plan has been announced.

“The response I get is a lot of citizens are getting tired of our spending pattern,” he said.

Dispatch services consolidation to be discussed

Councilors also agreed to discuss the possibility of consolidating the town dispatch with either South Portland and Cape Elizabeth or Cumberland County. Town Manager Ron Owens will develop an analysis for each alternative and one for taking no action.

This will be the first time the council discusses the potential for consolidating the dispatch services following an independent report that indicated it would cost $400,000 for equipment improvements to allow for the consolidation. Other costs such as staffing have not been identified.

The date for the meeting has not been set.

Comments are no longer available on this story