The town of Windham has hired Zoning Board member Ed Woodbury to oversee renovation of the Town Office annex.
To cut costs, the Town Council and Town Manager Anthony Plante decided against hiring an architect to develop specs for the renovation. In lieu of this, Woodbury will assume the role of project manager and work closely with a “project team” to guide the renovations and transform the old annex into more office space for the town.
Woodbury competed with Construction Management Consulting Services for the manager position. While the Bath, Maine-based consulting firm offered a price ($14,750) half the cost of Woodbury’s ($30,000), Woodbury had previously helped develop “conceptual layout” for the renovations and told the council he could complete the project for $240,000.
“I don’t want to prolong this much longer and we don’t have numbers from the other company,” said Councilor Carol Waig at Tuesday’s night council meeting before voting to hire Woodbury.
Woodbury did not however woo the entire council’s support. Council Chairman Robert Muir argued that hiring Consulting Services at the lower price would be more prudent.
“Looking at this as being ‘town money,’ I would like to get the most for it,” Muir said. “I’d rather see that $15,250 (difference) go into the actual building itself than as part of a management fee.”
In the interest of cost savings, Councilor David Tobin also proposed that Woodbury’s request for a “bonus incentive for completion under budget” be removed from his contract.
The council voted 5 to 1, with Muir dissenting, to hire Woodbury and his company River Road Common LLC to manage the renovation for $30,000 without bonus incentive.
Though Woodbury is on the Zoning Board, Plante said there is no conflict of interest in hiring him as the project manager and Woodbury is anxious to begin on the renovation.
“Weather’s closing in,” Woodbury said. “So hopefully we can get going.”
This is the first time, Plante is aware of, that Windham has undertaken a municipal renovation without the help of a professional architect. Instead, Woodbury and the “project team” will act as the architects and create proposals for building contractors who will work on sections of the renovation.
The project team will consist of Buildings and Grounds Maintenance Supervisor Dave Dickson, Community Development Director Roger Timmons and Plante himself.
Plante hopes to get started on the renovations right away. One of the first steps will be to demolish any unneeded interior walls, strip structural walls back to their framing and install new exterior windows, he said.
When completed, the town plans to move the tax collectors, town clerks, finance and town manager’s office into the annex space. Once these offices are moved, the remaining offices will be expanded or shuffled around to make the best use of space in the main building.
The main entrance to the town offices will also shift down to the annex. An interior stairwell will connect the annex to the main building and a “platform lift” will take mobility-impaired people from the ground-floor annex to first and second floor offices of the main building.
The annex renovation is projected to cost $270,000 with Woodbury’s fee included.
woodbury.jpg: Ed Woodbury talks to the Windham Town Council about plans for the annex renovation. Woodbury, also a Zoning Board member, was hired by the town to oversee the renovation as project manager.