THE FRANK J. WOOD “GREEN” BRIDGE, seen in this 2016 file photo.
THE FRANK J. WOOD “GREEN” BRIDGE, seen in this 2016 file photo.
BRUNSWICK

The Federal Highway Administration and the Maine Department of Transportation announced Tuesday that replacing the Frank J. Wood “Green” Bridge is their “preferred alternative.”

Several alternatives to replacement were considered, including rehabilitating the bridge.

A community group, the Friends of the Frank J. Wood Bridge, has been fighting to preserve the bridge. They argue the iconic bridge can be rehabilitated and its life extended upward of 75 years for a cost comparable to replacement estimates.

THE BRUNSWICK-TOPSHAM Bridge Design Advisory Committee has looked at preliminary design elements such as the one pictured here in its mission to work with the Maine Department of Transportation on a Frank J. Wood Bridge replacement design incorporating preferences of the surrounding communities. The committee will reconvene soon to finalize suggestions.
THE BRUNSWICK-TOPSHAM Bridge Design Advisory Committee has looked at preliminary design elements such as the one pictured here in its mission to work with the Maine Department of Transportation on a Frank J. Wood Bridge replacement design incorporating preferences of the surrounding communities. The committee will reconvene soon to finalize suggestions.
The Friends on Tuesday issued a statement expressing their disappointment at the MDOT’s announcement and said they would continue advocating for the bridge.

Advertisement

“MDOT has never seriously considered the rehabilitation option for this bridge and continues to use unverified assumptions on rehabilitation cost and future maintenance to skew the service life costs in favor of their ‘chosen’ alternative,” the group states.

The “preferred alternative” designation is a big step in an ongoing process to ultimately determine the bridge’s future, and comes after a months-long rigorous federal review process.

The final decision as to whether the bridge is rehabilitated or replaced may be forthcoming within a few months, once an environmental assessment is completed. An additional public meeting will be held prior to the conclusion of the environmental decision process.

According to MDOT, future studies will focus on the design and environmental impacts of replacement.

Key factors in the decision, according to a statement from MDOT, were the costs associated with servicing a rehabilitated bridge — which are more than double the replacement option costs — and the improved safety and accommodation of bicycle and pedestrian travel that comes with a new bridge.

According to MDOT, rehabilitating the 85-year-old bridge would cost an estimated $15 million — $17 million if adding a sidewalk, and prolong its life by another 75 years.

Advertisement

A replacement, to be built adjacent to and upstream of the existing bridge’s location, would cost an estimated $13 million and have a 100-year lifespan.

An MDOT work plan released in January has the replacement project slated to occur in 2018 or 2019 with $14.9 million in funding attached to the project.

The current bridge carries Route 201 over the Androscoggin River between Brunswick’s downtown and Topsham. Built in 1931, the 815-foot-long “Green” bridge had carried an average of 19,256 vehicles a day over the Androscoggin River, of which approximately 5 percent was heavy commercial trucks. In August 2016, the bridge was closed to large commercial trucks weighing more than 25 tons out of safety concerns.

The Maine Department of Transportation “looks forward to working with both communities to provide a bridge connection that not only meets the transportation needs, but is also befitting of this setting and environment,” its release states.

The Brunswick-Topsham Bridge Design Advisory Committee has some design suggestions, but did not finalize its recommendations pending the preferred alternative announcement, according to chairman Bruce Van Note.

Van Note said that “it would make sense to reach out to the Friends of the Frank J. Wood Bridge.” There maybe common ground, he said, regarding use of the public places near the site as well as memorializing the history of the bridge.

Advertisement

As MDOT produces more designs for the replacement bridge, Van Note predicted that “this can be a wicked cool bridge and I think it’s going to be something that people love.”

Go to maine.gov/mdot/env/frankj wood/ for more information.