A long-time advocate of the bridge also supports the reconstruction plan.
The Stackpole Creek Bridge, located on rural Simpson Road, is a non-engineered stone bridge built in 1848 with a unique keystone arch, which currently meets the criteria to be placed on the National Register of Historic Places. The bridge was closed to automobiles in 2013 after being deemed unsafe for vehicular traffic.
City officials have debated over the last decade whether to replace the bridge or restore it.
In 2014, residents voted to let the city borrow up to $990,000 to make changes needed to reopen the bridge, and the City Council later approved a restoration plan.
After it was determined the changes would cost more than originally thought, the council approved an additional $370,000 for the restoration that had previously been earmarked for other capital improvement projects.
But it was recently learned that the project approved by the city, which is set to begin this summer, would not meet criteria to qualify for the National Register of Historic Places.
The bridge currently allows water to flow through the keyhole arch and the stones around it. Under the reconstruction plans, the keyhole arch would remain, but the rest of the bridge would be demolished and a retention system with a stone facade made from the original stones would be installed.
Kirk Mohney, director of the Maine Historic Preservation Commission, sent an email to the city a few weeks ago stating that the bridge’s “integrity of design, materials and workmanship will be lost in the process,” thus making it no longer eligible for the historic registry.
Still, Mohney commended those who support the rehabilitation of the Stackpole bridge.
“While it may no longer be eligible for listing in the National Register after the current construction plans are implemented, Saco will still possess a visually distinctive bridge that incorporates an authentic 19th century feature into a modern structure designed to convey the general appearance of its 168-year-old predecessor,” wrote Mohney.
City Administrator Kevin Sutherland said the city has spent around $90,000 on engineering and design costs for the proposed reconstruction project, and canceling the contract now could have legal implications.
“It could get messy,” he said.
In addition, the low-interest rate obtained in a $450,000 state loan that the city secured for the bridge project expires if not implemented by April.
The project is scheduled to begin soon, and Sutherland said it needs to begin this summer to be completed by the fall.
“We’ve sat on this project long enough,” he said.
Inga Browne, a Simpson Road resident and member of The Friends of Stackpole Bridge, a local group that has advocated for saving the bridge, described the situation as bittersweet.
Browne said while it is disappointing to hear the bridge will not qualify for the registry, she said it’s “a small victory” that the arch will be preserved.
“It will still be a unique structure the city can be proud of,” she said.
She added that she thought CPM Constructors, who were not required by contract to produce a plan that would keep the bridge on the registry, rose to the occasion and created a plan that will rehabilitate the bridge so that it’s safe for modern traffic, has a 75-year life span, and will keep the unique keystone arch.
— Staff Writer Liz Gotthelf can be contacted at 282-1535, ext. 325 or egotthelf@journaltribune.com.
Comments are not available on this story. Read more about why we allow commenting on some stories and not on others.
We believe it's important to offer commenting on certain stories as a benefit to our readers. At its best, our comments sections can be a productive platform for readers to engage with our journalism, offer thoughts on coverage and issues, and drive conversation in a respectful, solutions-based way. It's a form of open discourse that can be useful to our community, public officials, journalists and others.
We do not enable comments on everything — exceptions include most crime stories, and coverage involving personal tragedy or sensitive issues that invite personal attacks instead of thoughtful discussion.
You can read more here about our commenting policy and terms of use. More information is also found on our FAQs.
Show less