Overhead sign foundation work along the Maine Turnpike median just south of Exit 44 is shown looking north. Existing signs on the turnpike are being replaced as part of a $1.59 million improvement project. COURTESY PHOTO/Maine Turnpike Authority

YORK COUNTY — About 18 percent of the third phase of a project to replace highway signs on the Maine Turnpike between Wells and Portland has been accomplished so far and it’s on track to be wrapped up by mid-November.

The project contractor is Liddell Brothers, Inc. and work consists of removing, replacing and installing new highway signs along the Maine Turnpike from south of Exit 19 to north of Exit 48 in the Wells to Portland segment of the Maine Turnpike.

Existing turnpike signs for the cities of Saco, Biddeford, South Portland and Portland and the towns of Wells, Arundel and Scarborough will be removed and replaced with newer and more efficient signs, turnpike officials say.

During the project, the contractor will furnish, install and salvage the existing aluminum signs, place new steel H-beam sign supports, install galvanized steel overhead sign structures, and place concrete foundations, concrete median barriers, and guardrail for maintenance of traffic while work progresses.

On Tuesday, the Maine Turnpike Authority announced that Liddell Brothers will be completing the median work for overhead sign foundations over the span of the next two weeks.

Advertisement

Once that work has been finished, work will start in installing ground mounted signs and work on the right shoulder for the overhead sign foundations.

Existing turnpike signs less than 12 feet wide will be disposed of by the contractor, turnpike officials said.

Liddell Brothers mobilized for the project in late April and has been working at night in the median construction on the new overhead sign foundations in the Scarborough area, along with two other locations they are currently working on.

The total cost of the project is $1,590,213 and was awarded by the Maine Turnpike Authority in February. It is part of the Turnpike Authority’s 2018 Capital Program which features  $87.8 million for construction projects and improvements on the thoroughfare.