4 min read

The 35-day partial shutdown of the federal government meant a projected January start for removal of asbestos and later demolition of the rear tower of the Stenton Trust building in Sanford,  shown here, couldn’t begin on schedule, but the U.S. Environmental Protection Agency says residents should begin to see activity at the site beginning in March. COURTESY PHOTO/Rolla Wells

SANFORD — The 35-day partial shutdown of the federal government played a role in the U.S. Environmental Protection Agency’s Stenton Trust project timeline, a spokesman said.

Now, the River Street remediation is set to move forward this spring with removal of asbestos in the front tower, called Tower A, and with a tentative May 1 start day to demolish the rear tower that burned on June 23, 2017.

The projected timeline has shifted a couple of times, from the summer of 2018, to the fall, and then to January. But the federal government shutdown that commenced at midnight on Dec. 22 and wound down on January 25 put an end to the January start.

EPA Region 1 spokesman Dave Deegan said residents will see activity around the site next month.

“One of the upcoming steps is that in March, EPA will install a pipe from the water line in the road to the site to get access to water, which will be required for asbestos removal activities,” Deegan wrote in an email. “After the pipe is installed and for several weeks in the spring, when the asbestos removal activities will occur, residents will see people in white suits and respirators entering the (front tower) building.”

Advertisement

He said there will be procedures in place to prevent any asbestos from being released from the building during removal, including wetting down the materials and creating a negative pressure environment within the space in which contractors will be working. As well, he said, the EPA will work closely with federal public health officials throughout the project, to ensure that activities conducted at the site do not pose health or safety concerns to the public.

Deegan said the demolition of the rear tower will take approximately four to six months.

The contractor overseeing the project for the EPA is Environmental Restoration, LLC. The company has previously performed work for the EPA in a number of regions, and is headquartered in St. Louis, Missouri, with regional offices in a number of U.S. cities, including Boston. Deegan said the contractor will be hiring several subcontractors for different phases of the project, in accordance with federal contracting guidelines.

Deegan said the EPA has estimated the cost of the project could be as much as $1.7 million.

As to the delay, Deegan said the EPA was not working during the shutdown and so couldn’t resolve a pending access issue, which has now apparently been dealt with, and that contractors could not work during the shutdown without EPA oversight.

City Manager Steve Buck told the Sanford City Council last week that he met with EPA site coordinator Christine Young, who was at the site in mid-February with an asbestos abatement company and a structural engineer.

Advertisement

He said Young told him that a temporary road will be installed for access by Central Furniture to their warehouse, located on High Street. Currently, a portion of the warehouse can only be reached through the Stenton Trust lot. Once the demolition project is complete, the temporary roadway will be removed, Buck said.

City leaders have long said that a developer has expressed interest in the front tower, which is closest to River Street. Buck told the council that the Maine Historic Preservation Office has confirmed that front tower can qualify as historic due to its architecture, paving the way for potential historic tax credits. A saw tooth roof building between the two towers is too far damaged to be preserved and will be demolished along with the rear tower.

Buck said once work begins, no further parking will be allowed on the site.

The arson fire that left the rear tower a skeleton of steel and concrete was so massive, it consumed 750,000 gallons of water. More than 100 firefighters from Sanford and several surrounding departments fought the blaze.

Three young boys, who were 12 and 13 years old at the time, were originally charged with arson in connection with the fire, and each later admitted to the lesser charge of criminal mischief and were placed on probation for a year.

Sanford’s assessing website lists Gateway Properties LLC as the owner, though the corporation, owned by Jonathan Morse of Reno, Nevada, no longer exists. Morse purchased the building in 1999 for $600,000, city records show. Current assessment for the property, including 6.8 acres of land, is $200,000. Property taxes have been unpaid for several years, and exceed $110,000.

Deegan said as work commences, an EPA trailer will be stationed at the front of the site.

“Residents can stop by the EPA trailer to ask questions and to get additional information throughout the demolition activities,” he said.

— Senior Staff Writer Tammy Wells can be contacted at 780-9016 or twells@journaltribune.com.

Comments are not available on this story. Read more about why we allow commenting on some stories and not on others.