KENNEBUNK — Two pieces of legislation proposed by Kennebunk organizations to change their debt parameters have been passed by the state Legislature. However, a change in law during committee for a law written by the school system left it impractical.
The first was a bill written by Superintendent Katie Hawes as RSU 21 was looking to pass a $55 million renovation bond. The bill, LD 1222, addressed the mechanism by which Regional School Units pay back bonds – allowing them to make more consistent payments over the life of the bond instead of front loading large payments initially.
This smoothing of the payment curve was meant to make the bond more palatable to residents by making the mil rate more consistent. However, the bill suffered a legal hurdle as it was vetoed by Gov. Paul LePage upon reaching Blair House. In the meantime, the renovation bond passed resoundingly with the old pay structure.
The Legislature did eventually overturn the veto, but Hawes said an addition made by Suzan Beaudoin, MDOE director of finance, during the committee back in May – that the consistent payment structure could only be used if it can save money – rendered the law useless to RSU 21.
“I think it is unfortunate that RSUs are unable to exercise choice in payment structures like municipal school districts,” Hawes wrote in an email. “The Maine DOE advocates for districts to come together to form RSUs but this kind of legislation presents a barrier to those districts that have followed through. I am unsure why the MDOE added this language to a bill that clearly addresses only building projects that are 100% locally funded.”
Since the bond passed and was not contingent on this legislative change, the RSU will move forward as scheduled.
“Our three communities voted in strong support of our building projects before this LD 1222 passed, anticipating the traditional, and fluctuating, ‘level principal style’ bond,” Hawes wrote.
The other legislation was an overhaul to the charter of the Kennebunk sewer district which involved raising the debt limit. The bill, LD 1223, brought the charter of the district up to code with the model provided by the Legislature, and raised the debt limit to $30 million (providing a structure by which the town may choose to raise the debt limit). This change is primarily to accommodate the anticipated construction of a new treatment plant because of new regulations and equipment limitations.
“New limits hit equipment in place and we have some biological limits,” Kennebunk Sewer District Manager Michael Boulduc said. He explained that equipment currently was at around 90 percent of capacity, and that $5 million is already being spent on the design of the treatment plant that would discharge into the Mousam River. Boulduc added it was too soon to say when the plant would go under construction, but it would be “much sooner” than 10 years.
Comments are not available on this story. Read more about why we allow commenting on some stories and not on others.
We believe it's important to offer commenting on certain stories as a benefit to our readers. At its best, our comments sections can be a productive platform for readers to engage with our journalism, offer thoughts on coverage and issues, and drive conversation in a respectful, solutions-based way. It's a form of open discourse that can be useful to our community, public officials, journalists and others.
We do not enable comments on everything — exceptions include most crime stories, and coverage involving personal tragedy or sensitive issues that invite personal attacks instead of thoughtful discussion.
You can read more here about our commenting policy and terms of use. More information is also found on our FAQs.
Show less