GORHAM — Town officials will learn Thursday details of Harvey Performance Company’s plans to construct a large facility at the former horse racing track off Narragansett Street.
The precision toolmaker’s facility would be built on a portion of the 62-acre former race track that Moody’s Co-Worker Owned Inc. acquired from Hannaford in 2016 for a business park.
Shawn Moody of Gorham, founder of a chain of auto collision repair centers and former gubernatorial candidate, said Tuesday the Harvey project would be situated close to the rear of the former track site and accessed from Narragansett Street (Route 202). Moody said the deal represents the first sale at the park. “It’s nice to get some activity,” he said.
Harvey plans a 76,000-square-foot facility with 170 parking spots, according to a report from the Portland Press Herald.
Harvey has a plant, Helical Solutions, in the Gorham Industrial Park. Plant manager Adam Martin referred questions about the proposed project to Garth Ely, vice president of marketing at Harvey, but Ely didn’t return a telephone message Wednesday by the American Journal’s deadline.
Tom Ellsworth, Gorham Economic Development director, said he and other town officials would meet informally with company representatives Thursday, Nov. 29, to hear about the proposal.
Moody said a public meeting with Harvey representatives about is set for 5-6:30 p.m. on Thursday, Dec. 6, at Moody’s Collision Center, 200 Narragansett St., a short distance from the former race track.
The project would require local Planning Board approval and a permit from the Maine Department of Environmental Protection. It would not likely be on a town agenda until after the New Year.
The Narragansett District is served by public water, sewer and industrial electrical service. David Galbraith, Gorham zoning administrator, said Tuesday an effort is underway to extend Maine Natural Gas service on Narragansett Street from State Street.
Galbraith estimated a gas extension would cost $800,000 and the gas company would put up $700,000. Gas could serve Moody’s proposed park, other businesses, Southern Maine Community Recreation Center’s sports dome and up to 75 homes, Galbraith said.
Test borings could begin next week, Galbraith said. An installation project would take about eight weeks and he said Portland Water District could also replace water lines in that area.
The Town Council in October approved zoning changes for the Narragansett Development District to allow residential units above businesses and buildings up to 50 feet high. The district runs along a stretch of Narragansett Street from the roundabout on the Bernard Rines Bypass.
The former race track site is in the district and about one mile from Gorham Village. Moody said he’s had several inquiries about lots in the business park.
Galbraith said, “It is one of the most marketable properties in town.”
The site is at the Narragansett Street roundabout of the bypass that could be linked with a future spur to the Maine Turnpike.
Robert Lowell can be reached at 780-9089 or email rlowell@keepmecurrent.com.