Closure of the final portion of the Freeport landfill is scheduled to begin next month.
The town was scheduled to select a bid this week for a contractor to close the landfill off Pownal Road. A request for bids was issued in February, when the Town Council approved the shutdown.
The construction and demolition debris landfill, at the town’s transfer and recycling center on Hedgehog Mountain Road, was created in 1978. The municipal and solid waste portion of the landfill closed in 1990. Throughout the 1990s the debris landfill underwent phased closing.
The Maine Department of Environmental Protection in March approved the Town Council’s request for final closure. The DEP also approved the town’s post-closure maintenance plan, which says the town will inspect the landfill semi-annually for the first two years after the closure and annually after that.
A state engineer will be assigned to assist with the project.
According to the town’s request for bids, the landfill must be closed with a “layed soil cover system,” with an 18-inch layer of clay soil and a six-inch layer of topsoil on which grass can grow. The existing cover on the already closed parts of the landfill must also be regraded.
Also, trees and brush on the covered parts must be cut down and compacted.
The closure process is expected to begin by May 12 and be completed by Oct. 6. Town Engineer Albert Presgraves and Facility Manager Suzanne Duplissis could not be reached Monday.
The estimated cost of the project is unknown. The Town Council could select the final bid at its meeting Tuesday, after the Tri-Town Weekly’s deadline.