WESTBROOK – Neighbors on both sides of the now divided Duck Pond Road neighborhood, see the merits of building a new bridge across Mill Brook Stream, but some wish there was a way to get across the stream in the meantime.
Last week, crews from the Maine Department of Transportation razed the Whitney Bridge, cutting off traffic on Duck Pond Road out to Route 302 on one end of the 4-mile roadway.
While construction takes place on building the replacement bridge, residents have no way to cross the stream and get to the nearby convenience store, church and other businesses on Route 302.
And according to Eric Dudley, city engineer, there are no plans in place to put in a pedestrian bridge for the public use, due to cost and liability concerns, further outraging some residents.
“There’s no footbridge out there and people are talking about crossing the dam. That’s a very damaging thing to do,” said Mike Sanphy, the city councilor whose ward covers Duck Pond Road. “It’s creating a problem. One guy said he had to drive four miles to get to the store. A community divided is a bad thing.”
In an email to city administrators last week, Dudley said he has heard the mounting concerns, but the cost and time commitment would nearly double if a pedestrian bridge were added to the scope of the project.
“In order to provide public access for pedestrians, we would need to fully design a structure to support pedestrian loads. The bridge would need to meet ADA standards which would be extremely difficult given the constraints of neighboring properties and the steep terrain in the area. The bridge would therefore need to be quite long which significantly increases costs. Additionally, the bridge would need to be built above the flood plain which has other design considerations,” Dudley said in his email.
According to Dudley, the cost of the bridge project stands at approximately $200,000. In order to develop a pedestrian bridge, an additional survey, geotechnical and structural design and legal work would bump the cost up significantly. For example, the cost of the proposed pedestrian span on Bridge Street will cost $285,000 to fabricate, which does not include design work, building costs or abutment work. While a temporary bridge could be made for less, Dudley said, it would not be significantly less.
The length of the project would also increase from the anticipated eight to 10 weeks of construction to 12-16 weeks, and could affect school traffic when the school year begins this August.
A quick timeline was one of the biggest selling points for Dave Gowen, a neighborhood resident.
“I wasn’t expecting it [a pedestrian bridge] at all. It doesn’t bother me in the least. I just want the bridge done on schedule and on time,” said Gowen. “We’re only a couple of houses up from the bridge and the biggest inconvenience is we have to drive to Elmwood. We don’t have any cars going by right now so it’s nice and quite. I think they’re doing a great job. They did everything they said they would do with putting out the signs and they’re not working at night.”
But, for neighbor Bruce Vanni, the missing span is problematic, even if it is just for the summer.
“In one way it is inconvenient. There is no access to Route 302 and the store. We use that store a lot for gas and odds and ends. We take the grandkids for ice cream up there. Our church was .2 miles away, but when you go the other way [traveling down to Elmwood Avenue to reach Route 302] it’s eight miles. That’s inconvenient,” Vanni said. “I asked about a footbridge. If the workman can walk across it, why can’t we?”
Vanni said he understands the city’s concerns about liability.
Sanphy said he continues to hear complaints from area residents who want to see a footbridge added to the project, including a blind man who now can’t walk to the store, losing his “social link.”
“People are getting upset up there. It’s a community divided. This is not the day and age for a Berlin Wall. I’m upset about it, too. It irritates me,” Sanphy said.
Mike Bradshaw, superintendent of the project, said as of now there are no plans to allow people to access the walkway used by the construction team or build a pedestrian bridge.
He said he expects the project to be completed in nine more weeks.
The June 19 demolition of the Whitney Bridge on Duck Pond Road leaves area residents without a walkway to Route 302 businesses until August. Courtesy photo