WESTBROOK – Work has begun on the second phase of a nearly four-year process to renovate Westbrook’s Walker Memorial Library, and is seen as a major step toward updating and attracting more patrons to the historic building.

The original 120-year-old brick structure, highly visible from Main Street with its unique architectural style, has gone without significant upgrades for years, and is mostly cut off from regular visitors, who use the library’s expanded portion set back from Main Street.

Phase 2 of the renovations began last week and is slated to be complete by late June. This phase, seen as a major hurdle in the process, is a complete overhaul of the lower level, which will serve as the staff offices and break room. The floor has been closed since 2010 when work began on the exterior of the building.

“We’ve been waiting, step by step, but this is the end of Phase 2 of the project,” said Karen Valley, Walker library director.

Valley said that on May 26, the library will celebrate its 120th anniversary. The library opened in 1894, owing in large part to a $40,000 posthumous donation from local businessman Joseph Walker.

Walker left the money for the purpose of establishing and maintaining a free public library in the city, and succeeded. Walker is one of the four oldest libraries in the state and was placed on the National Register of Historic Places in 1980.

Advertisement

According to City Engineer Eric Dudley, in 2010, the city of Westbrook “embarked on a comprehensive process” to restore and renovate the original Walker Memorial Library structure in response to concerns about its condition at that time.

Dudley said the evaluation in 2010 pointed to significant deterioration, including leaky roofs, window failures, lack of foundation drainage, mold, lead and asbestos hazards, along with inadequate heating, ventilation and electrical service.

The first phase of the renovation work, completed in 2011 by Great Falls Construction of Gorham, cost about $411,000. According to Dudley, the company removed and rehabbed the original slate roofing, installed new copper gutters, repainted the brick walls, repaired and replaced all exterior woodwork, reinstalled the original granite front steps, and installed a new, state-of-the-art foundation drainage system.

Valley said that as part of the work, each window was removed and restored to standards held by the Register of Historic Places.

For the employees of the library, who have put up with makeshift employee offices on the second level, the noise of the work is a welcome sound.

Julie Peterson, the curator of Walker’s local history room, said last week that she doesn’t mind the rumbling below her office, and anxiously awaits work to be completed.

Advertisement

“We’ve been displaced into a lot of different parts of the library,” Valley added.

Judith Reidman, the chairwoman of the Walker Board of Trustees, said the process has been long, but necessary.

“We’ve been writing as many grants as possible to pay for the process,” she said. “Money is always what holds you back.”

Reidman said the library staff and board are grateful to the city for its help in the renovation process.

“The city has helped tremendously, or we wouldn’t have got this far,” she said.

Dudley said that in July, after work is completed, Walker employees will have new workspace, volunteer workspace and book processing area, as well as a kitchen, bathroom and break room.

Advertisement

“Along with this, the electrical system and life safety system are being fully upgraded in the historic section of the building,” he said.

A chunk of funding for the project has come from Friends of the Walker Memorial Library, the nonprofit fundraising entity of the library. H.E. Callahan of Auburn is completing the second phase at the cost of $157,000. Donations received by the Friends of the Walker Memorial Library have reached $77,875.

To date, the total project costs are about $981,000, which have been offset by $212,000 in grants and donations. Major grants have included $85,000 from Efficiency Maine toward a new HVAC system and a $50,000 Steven and Tabitha King Foundation grant toward the historic windows.

Although the city will cover most of the remaining costs, the library’s Gerald Fluett Trust Fund has paid $260,000 since 2010 toward the project’s outstanding debt. An agreement was reached between the city and library board of trustees when renovations first began that the city pay off debt using interest generated by the trust fund.

“Although there will still be work left to be done at the end of H.E. Callahan’s project,” Dudley said, “the vast majority of improvements to the 1894 section of the library will be completed.”

Reidman and Valley are hoping that once Phase 2 is complete, more excitement will be felt throughout the community.

Advertisement

“I think once they can see something, people will get excited about it,” Reidman said. “We’re hoping once they see the downstairs, we’ll have more support.”

The final phase of the project will complete the upstairs portion of the old building, with new carpeting, woodwork, painting and more cosmetic work such as lighting, but Reidman said the work would have to wait until further funding is in place.

Valley, who recently announced she is retiring at the end of June, said that while she won’t oversee the final phase, she will still be involved in the Walker community and looks forward to see the finished product.

“I live in this community, and I want to see that it’s successful, obviously,” she said.