4 min read

Infobox:

Here is how the South Portland School District and Harriman Associates break down costs for renovating and rebuilding South Portland High School:

A. Construction: $46 million. This includes new building construction, demolition, renovations, installation of artificial turf on football field, site work, replacing utility lines, adding a traffic signal.

B. Administrative costs and reserves: $5.4 million. The price tag covers technology upgrades, asbestos abatement, portable classroom rental during construction, equipment purchases, insurance, legal ads and costs for attorneys.

C. Fees and services: $3.9 million. The money pays for architect and engineering services, environmental permits, surveys, soil testing, traffic studies.

The South Portland City Council is asking a lot of questions about – but offering little opposition to – a major renovation proposed for South Portland High School.

Advertisement

The council is expected to decide this month whether to allow an $85 million bond referendum to appear on the November ballot.

Roughly $55.6 million would cover the school’s reconstruction costs, with an additional $29.4 million in interest fees on a 20-year bond.

“If I had to guess, I would say that the renovation plan will be approved by the council, and put out to the people for a vote,” said Councilor Jim Hughes. “From there, it is hard to know how voters will react, given the cost for rebuilding.”

At issue is a plan to renovate and expand the city’s only high school, off Highland Avenue. The school was built in the 1950s, with additions made over the years.

“I sat on the facilities committee that studied the building project for two years. I certainly did not know what the magic number would be, in terms of construction costs,” said Councilor Maxine Beecher. “I did learn that the school is certainly in need of vast improvements and repairs.”

Beecher and 25 other members of the committee worked for two years to identify problems at the 1,000-student high school and come up with the reconstruction plan for addressing them.

Advertisement

The committee’s findings show problems with mechanical and fire-safety systems that are near the end of their service life and at risk of failing building codes.

During recent informational sessions and a high school tour, the council learned about the committee’s findings and recommendations for a new school building.

The new construction would be done in phases, with the target date for completion in 2012. A major component would be installing underground water retention systems and redirecting storm drainage away from the site.

The existing building has standing water in some areas, and water damage on floors and walls.

Plans also call for demolishing and rebuilding most of the classroom space. The rest of the facility would be renovated. The new high school would house 1,200 students, with a center courtyard to allow sunlight in classrooms and save on utility costs.

Here is a breakdown of some major costs and what they cover:

Advertisement

• New building construction, $30 million: Building additions include classrooms, a new library, science wing, cafeteria and kitchen, boiler plant, rebuilt entrance on Mountain View Drive, a single-story gym with locker rooms, weight rooms and exercise room.

• Building renovations, $7.5 million: Existing buildings would be gutted, with asbestos removed from floors and ceilings. The buildings would get new windows, insulation, drywall, flooring, ceilings, mechanical and plumbing systems. Life safety upgrades also would be made.

• Site development, $5.1 million: Major sitework would include reinforcing and replacing existing foundations. Utilities would be upgraded with underground gas and water from Evans Street to a new boiler plant location. There would be new underground drainage for a football field with artificial turf. Ledge would be excavated to allow for a retention pond to be dug.

Superintendent Wendy Houlihan said this week that she was pleased with the architectural work by Harriman Associates and its efforts to educate councilors about the project, its costs and the work ahead.

“The council had their second workshop Monday, and the members posed great questions,” said Houlihan. “It seems that the architects were able to clarify several issues for them. I would characterize it as very positive.”

Houlihan said Councilor Linda Boudreau had questioned at workshops whether the school district should scout for an alternative site for a new high school, because of costly problems with drainage and ledge.

Advertisement

But an architect from Harriman Associates explained that there are few undeveloped sites left in South Portland.

Wainwright Fields, for example, has deed restrictions that preclude a school construction project.

The city also has a significant investment in the existing high school campus, such as a fairly new auditorium, and a track and field complex with bleachers.

“The real question for voters is whether a new high school will be a better place to learn for the kids, well into the future,” Hughes said. “That’s up to the parents – and the voters – to decide.”

The first reading of the proposed bond issue could be as early as Monday, according to the City Clerk’s office. After the city council has its first reading of the bond, a public hearing will be scheduled.

Even if voters rejected the referendum, the city would incur costs for bringing the existing building up to code for such issues as handicap access and water runoff.