Two road projects started last year in Freeport will be completed early this summer, while pending jobs in both Freeport and Durham are subject to approval by the governing bodies in those towns.

Earl Gibson, superintendent of Freeport Public Works, said his crew will finish up a major job started last year on Wardtown Road (Route 25). Once that project is complete, Gibson said, Public Works will complete a job on Litchfield Road.

Then, projects clamored for in South Freeport will depend on the Town Council’s treatment of the capital budget plan. Town Manager Peter Joseph will reveal the five-year capital program to the Town Council on Feb. 26. A public hearing on the capital budget is set for April 7, and the council will adopt the five-year capital program on April 14.

Reconstruction of Wardtown Road began last year. The town’s share of the job is $800,000, with the state providing $500,000. Gibson said that work on the final surface probably will begin in May.

“That’s going to be weather dependent,” he said. “Once the weather’s clear and the temperature goes up, we’ll put a surface on that road.”

One lane of traffic will be closed during paving, which should take only about three days, Gibson said.

Advertisement

Following Wardtown Road, the Freeport Public Works crew will lay down a surface on Litchfield Road, which Gibson says should take just two days.

Then comes a project beginning right outside the Public Works offices on Hunter Road, a project that will not be measured in days.

“We need to do ditching, culvert replacement and then a base overlay,” Gibson said. “It will be the whole length of the road. It’s a pretty good little project.”

Al Presgraves, town engineer, said that the Hunter Road work will come out of an annual overlay account, which now has approximately $425,000.

“That will pretty much take the whole allocation,” Presgraves said. “It comes under the operating budget.”

Hunter Road is 2.6 miles long, and becomes Merrill Road in Pownal.

Advertisement

“Pownal wants to overlay their section of the road at the same time, to get a better price,” Presgraves said.

On some stretches of Hunter Road, traffic will be reduced to one lane.

“That’s going to take most of the summer,” Gibson said. “While we’re doing that we hope to begin on South Freeport, too. But that’s up to the council.”

Gibson said that Main, Middle and Park streets in the section of Freeport near the town wharf – busy with vehicles hauling boats all summer – are in need of reconstruction.

“If we get approval,” Gibson said, “we’re probably not going to start construction in South Freeport at least until after September. I want to get by Labor Day and let some of the traffic die down.”

A well-traveled Freeport sidewalk will be elongated this summer. The Maine Department of Transportation will add to a stretch of sidewalk on South Street in July, a project with a price tag of $100,000 partially funded by the state.

Advertisement

“This will make the sidewalk go from School Street all the way to West Street,” Gibson said. “We put the sidewalk on West Street last year, so that will tie those projects together. The short section of South Street doesn’t connect – it’s just dirt.”

Gibson said he sees no issue with foot traffic during the sidewalk job, which should take two to three weeks.

In Durham, people who travel near Runaround Pond and on Rabbit Road are calling for road repairs. Calvin Beaumier, road commissioner for Durham and Pownal, said he made presentations to the Durham Board of Selectmen last week. Beaumier is hoping that the board will place his request for those two jobs on the April 2 town meeting warrant. The town probably would consider taking out a bond, he said.

Beaumier estimated that the Runaround Pond and Rabbit Pond projects might cost around $1 million if the town hires a contractor – less if the town crew does them.

“There’s lots of public demand,” he said.

If approved, a section of road from Route 136 to Runaround Pond Park would be reclaimed, along with shoulder work and repaving, Beaumier said. From the park to the Pownal line, workers would reclaim the surface, then apply a cement or asphalt injection.

“That will be one project, in two different sections,” he said. “That piece from Runaround Pond to the Pownal line is much worse. The next recommendation would be Rabbit Road. We’d do the same process there – reclaim and then pave.”

Beaumier said the work on the Runaround Pond project is dependent on how long it takes to obtain the bond, if accepted by voters at the town meeting.