The Maine Department of Transportation announced Wednesday that Shaw Brothers Construction submitted the lowest bid of $10.2 million on the long-awaited Gorham bypass project.
The company anticipates starting the job as soon as next month. The state plans to award the contract this month.
“We gave it our best shot and a little more,” Jon Shaw, co-owner of the construction company, said Wednesday. “We like to work close to home. It means a lot for our people to be home at night.”
“I’m ecstatic to have a local company get it,” Norm Justice, chairman of Gorham’s town council, said Wednesday following the announcement.
The 3.4-mile bypass south of Gorham Village is aimed at reducing the rush-hour congestion in Gorham’s downtown. It would also reroute trailer trucks, which include gasoline and oil tankers that pose a safety hazard downtown. There are an estimated 40,000 cars and trucks motoring daily through the village square, where routes 25 and 202 merge with 114.
Relief of bumper-to-bumper, rush-hour congestion has been years in the planning. Burleigh Loveitt, vice chairman of the Gorham Town Council, said Tuesday a Gorham selectman, Austin Alden, envisioned a bypass in 1952 and laid out a path similar to the one approved.
“It has taken 55 years,” said Loveitt, who served on the committee that planned the bypass. “This is a defining moment for Gorham.”
Three bids for the bypass were opened at 11 a.m. Wednesday in Augusta. John Stanley, a spokesman for the Maine Department of Transportation, said Sargent Corp. of Stillwater was second with a bid of $11.8 million followed by R.J. Grondin & Sons of Gorham with a bid of just under $12 million.
For part of the bypass project, the state accepted separate bids to build a bridge on Flaggy Meadow Road, and four were submitted. Stanley said the lowest for the bridge came from Technical Construction of Turner with a bid of a little less than $1 million.
The Maine Department of Transportation estimated the bypass would be completed by June of 2009. But if all goes well, it could be finished as early as the fall of 2008.
But the bypass doesn’t eliminate all of Gorham’s traffic woes. “It’s the beginning of solving the traffic problems,” Justice said earlier this week.
A northerly bypass of Gorham Village hasn’t been approved. Justice said the southerly bypass would relieve safety fears caused by big trucks that now have to turn in a tight space in the village intersection.
“The biggest thing is to address safety of truck traffic in Gorham Village,” Justice said.
Construction start of the bypass is good news for many residents and motorists in Gorham. Sara Roberts of Gorham, a student at the University of Southern Maine, said the bypass sounds like a good idea. She said the downtown intersection is dangerous and hazardous for pedestrians trying to cross.
“I’ve had a few close calls,” Roberts said.
Lillian Gritter of Windham, an employee at a downtown coffee shop, said she thought the bypass would help relieve village congestion, which deters potential customers.
“Big trucks fly around these corners,” Gritter said. “People are excited about (the bypass) for a less congested intersection and a more accessible downtown.”
The bypass will skirt Gorham Village, linking South Street (Route 114) to Route 25 at Brandy Brook Hill. It will intersect at Narragansett Street (Route 202) and will pass under Flaggy Meadow Road, which will have a bridge. Webster said Flaggy Meadow Road would be shut off and traffic detoured for six months next year.
The bypass will have a 12-foot-wide travel lane in each direction with paved shoulders 8 feet wide. Bicycles would be allowed on the highway.
The right of way would accommodate future expansion of the highway to four lanes. The highway is designed for 55 miles per hour. Businesses will not be allowed access along the path. Access to the bypass will be limited to the three intersections.
Ralph Webster, assistant project manager for the Maine Department of Transportation, said the three intersections will have roundabouts, improved versions but similar to the existing one in Little Falls at the intersection of routes 202 and 237.
Roundabouts are designed to keep traffic flowing as opposed to an intersection with stoplights. Webster said the three roundabouts would be small but would accommodate trailer trucks.
David Irving, who lives on Ossipee Trail, thinks the roundabout on top of Brandy Brook Hill is misplaced.
“I’ve sat in my driveway some days for 10 minutes waiting to get out,” Irving said, and thought the Route 25 roundabout would lead to accidents.
Irving said the roundabout would slow big truck traffic and would be dangerous especially in icy, winter conditions. He also said the vision of eastbound, early morning commuters on that hill is impaired by the sun.
Irving said a bypass route should have begun near the intersection of Wood Road at the foot of Brandy Brook Hill and connected with Route 22 instead of South Street. “I think it’s the biggest joke,” Irving said about the bypass.
Pauline Washburn of Washburn Drive said the bypass was designed to get big trucks out of the village. She lives near where the South Street roundabout will be located and she said the roundabout would slow big trucks and the traffic flow there.
Washburn said effectiveness of the bypass would hinge on whether it would someday be linked with a spur to the turnpike.
Transportation officials recognize problems in the area of routes 22 and 114. “We have bottlenecks to deal with in South Gorham,” Justice said.
The bypass will be paid for by state and federal money. Two years ago, U.S. Rep. Tom Allen earmarked more than $15 million for the bypass in a transportation bill passed by Congress.
Comments are no longer available on this story