WESTBROOK – With stage one of the Walker Memorial Library renovation project nearly finished, and stage two about to begin, city officials are now turning their attention to the final piece of the extensive updates to the 19th-century city landmark.

The City Council moved unanimously, with Councilor John O’Hara absent, to give preliminary approval to hire Russell A. Martin P.E., of Freeport, to design a new heating and air-handling system for the library. The council will have to vote on the measure again at a future meeting to make it official.

The current system uses an old oil-fired boiler with an outdated steam heat distribution system, said City Administrator Jerre Bryant.

“The heat distribution is horrible,” he said. “It’s horribly inefficient.”

If approved, the engineering contract will cost $3,500. The money, according to Bryant, will come out of the 2010 capital improvement bond, which has paid for $675,000 of the library project so far.

The first stage of the project, which is expected to be finished late this summer or early in the fall, involved repairing, and in places rebuilding, the fac?ade of the oldest part of the 1894 structure. The effort will weatherproof the building, which has leaked for years, and replace ornamental details like copper finials, some of which were hand-carved.

Advertisement

After sealing the building, the next step will be to repair the damage done by the water. Specifically, the council has approved a $26,000 project to clean up mold that has appeared in older portions of the library, due to decades of water leakage.

Now, the city is working on the heating system. Right now, the building uses an old oil-fired heating and air-handling system, which city officials said is badly in need of replacing.

The exact cost of the boiler is not yet known, Bryant said, but the city has earmarked $85,000 of the bond money to help pay for it. An additional $85,000, Bryant said, is available from the Maine Energy Efficiency and Conservation Block Grant. The grant is awarded to projects that can demonstrate energy savings, so Bryant said the boiler project qualifies.

“We will save significant heating dollars,” Bryant said.

Once the bonded repairs are complete, Library Director Karen Valley said she wants to raise funds to do work on the interior. Parts of the original structure, she said, have been closed off ever since the library absorbed the collection from the Warren Memorial Library, which closed in 2009. The closed area includes two large reading rooms located just inside the building’s front doors.

While not moldy, Valley said, the room is stained from years of water damage. The other room, known as the local history room, contains some of the city’s oldest documents and photographs. Valley said it needs updated collection security so the room itself doesn’t need to be kept under lock and key.

Valley said she also wants to see some of the furnishings in the older part of the building replaced, so that the staff can relocate back to the ground floor, and the reading rooms can reopen to the public again.

The exact financial goal is not known, but for now Valley and other library officials and the Friends of the Walker Memorial Library are creating a fundraising committee.