BRUNSWICK — The Maine Department of Transportation says it has found enough safety and traffic issues at the Maine Street Bridge in Brunswick, also known as the Route 1 overpass or the Pool Table (because of its large rectangular shape), to warrant replacing it at a cost of up to $10.6 million.
“Everyone knows the problems that exist at the pool table,” said Tom Errico, a transportation engineer with T.Y. Lin International, which conducted the feasibility study on the project. “From a safety perspective it is quite frankly a disaster and operationally it doesn’t work.”
T.Y. Lin and Maine DOT officials looked at multiple options to help ease traffic congestion, improve safety, maintain access to businesses at Fort Andross, work with the Androscoggin Riverwalk and stay cost-effective, Errico said.
The preferred option is a $5.8 million project which would combine the Route 1 Southbound on-ramp and Cabot Street with a single signalized intersection at Fort Andross and a signal at Mason Street. The parking would have to be reconfigured at Fort Andross, splitting a small section of the lot, but it would still maintain access for businesses and accommodate the Riverwalk.
Officials also looked into a roundabout, Errico said, but it would have required two lanes to accommodate the level of volume. It would also create problems for pedestrians trying to cross, and at $10.6 million, it was the most expensive option.
The third option, a single point urban interchange would create a signalized intersection and reintroduce the Mill Street movement to Topsham by allowing a left turn from the Route 1 off-ramp onto Maine Street. This $7.8 million project would “move traffic very efficiently” Errico said, but would prohibit left turns in and out of Fort Andross, which was a “significant concern” for the businesses.
Errico estimated that just under 200 vehicles per hour would shift to this option instead of driving down Pleasant Street and turning left onto Maine. While any “reduced volume on Maine Street is a good thing,” it was not as much of a difference as he expected, he said.
The Department of Transportation favors the first option and is willing to contribute up to $5.9 million to whichever project the town chooses.
The designs still need to be ironed out, according to Nate Howard, a transportation planner with MDOT, and construction likely will not start until 2022.
If the town chooses not to proceed with any of the options, MDOT will still re-deck the Maine Street overpass.
Comments are not available on this story. Read more about why we allow commenting on some stories and not on others.
We believe it's important to offer commenting on certain stories as a benefit to our readers. At its best, our comments sections can be a productive platform for readers to engage with our journalism, offer thoughts on coverage and issues, and drive conversation in a respectful, solutions-based way. It's a form of open discourse that can be useful to our community, public officials, journalists and others.
We do not enable comments on everything — exceptions include most crime stories, and coverage involving personal tragedy or sensitive issues that invite personal attacks instead of thoughtful discussion.
You can read more here about our commenting policy and terms of use. More information is also found on our FAQs.
Show less