YARMOUTH — The state says it expects to invest more than $8 million to rebuild the Exit 15 interchange on Interstate 295 next year and make improvements to the park-and-ride lot off Route 1 in Yarmouth.

State planners say the improvements are needed to make travel safer and reduce the number of drivers who use Route 1 in Yarmouth to reach Exit 17.

Under the current system, drivers going north on Route 1 from Falmouth cannot get on I-295 northbound from Exit 15. The only way to get onto the northbound side of the interstate is to keep driving north to Exit 17, near DeLorme.

The reconstruction project will create a new northbound entry to the interstate at Exit 15 and create spaces for more than 300 cars and buses at a new park-and-ride lot beside the southbound interstate entry off Route 1.

The Maine Department of Transportation will also redesign the southbound entry ramp by lengthening the approach, a change that engineers believe will reduce the number of accidents that occur when drivers try to merge with Interstate 295 traffic.

“It’s a fast way to get on the interstate, but it’s also a dangerous way to get on,” said Mark Debowski, one of the project designers.

Advertisement

State officials presented their plans for the project during a public hearing Tuesday night at the Log Cabin in Yarmouth. It was the first presentation since the state took public comment on its initial plans in November 2010.

Improvements to the Exit 15 Interchange will cost $6.8 million, and the new park-and-ride lot will cost $1.3 million. The projects will be funded with federal and state highway improvement money.

The state says that, on average, about 3,800 vehicles per day use the Exit 15 northbound exit ramp. Officials predict that more than 5,000 vehicles per day will use the new Exit 15 northbound entry ramp.

“The big secret behind this project is to alleviate the congestion we are seeing at Exit 17,” said Ernie Martin, who is managing the road improvement project for the MDOT.

Martin said the improvements in Yarmouth represent one of the largest projects on I-295 in recent years. He said the biggest challenge to creating a northbound entry point is a huge outcropping of ledge that will have to be blasted.

“There is going to be a lot of blasting on this project,” Martin said. Blasting may require temporary shutdowns of the northbound exit ramp.

Advertisement

The MDOT will accept bids for the project in December. Construction is expected to start in the spring of 2013, with the project being completed by the fall of 2013.

Overall, the response to the project was favorable Tuesday night.

Steve Woods, chairman of the Town Council, praised the state for developing a plan to reduce the amount of traffic that passes through Yarmouth on its way to Exit 17.

“I think these improvements will add value to our community and will make it safer,” he said.

“This is going to be fantastic,” said Craig Martin of Yarmouth. “I’ve seen some pretty horrible accidents out there.”

Tony Donovan of Portland, who represents the Maine Rail Transit Coalition, argued that the project is unnecessary, especially during a period of economic uncertainty.

Advertisement

“In a time when public dollars are scarce, I can see no reason for this to be done,” Donovan said. “Maybe it’s not the most effective use of our tax dollars.”

 

Staff Writer Dennis Hoey can be contacted at 791-6365 or at: dhoey@pressherald.com

 