WESTBROOK – Opponents to the Spring Street quarry operated by Pike Industries Inc. say they will take the company to court for a second time, this time after losing an appeal to the Zoning Board of Adjustment.
“That just proved the point that this property now has immunity,” Warren Knight, a member of the family that owns Smiling Hill Farm, said of the Pike quarry in reaction to the board’s decision at its July 6 meeting.
Knight and Tim Bachelder, who represented residents in the city’s Birdland neighborhood, addressed the board at the meeting, asking to appeal a decision made by City Engineer Eric Dudley to allow the company to build an access road to the quarry and conduct construction blasting at the same time.
Dudley said he granted Pike permission to build the access road, and conduct blasting necessary to do so, in accordance with a controversial consent agreement reached between Pike and the city last fall, which dictates when and how Pike may use the quarry.
The zoning board voted to dismiss the objection to the blasting, ruling unanimously that no decision was required on that aspect of the appeal since by July 6, Pike had finished its construction blasting, and there was nothing to appeal.
The board also voted unanimously to dismiss the appeal of Dudley’s decision to allow Pike to build the access road, which the company is still working on. According to the motion, the board determined that it had no jurisdiction over Dudley or the consent agreement.
Knight said he and the Birdland group, who are already appealing the legality of the consent agreement, plan to take their contention that the agreement violates city law to court as a separate lawsuit. No paperwork has yet been filed in the case, Knight said.